National Highways Developement Project - Phase III
Status as on 30th June 2015

S.no

Stretch

NH No Length
(Km)
Total Project Cost (Rs.Cr.) Funded By Award Date Date of Start MM/YYYY Date of Completion MM/YYYY Contractor/Concessionaire & Nationality


Supervision Consultant/IEC &Nationality
Status
1
Four Laning of Solapur - Bijapur
13
109.08
1377.54
BOT
May 2015
Uniquest Infra Ventures Pvt Ltd-Indian


-
Under Implementation
2
Four laning of Patna - Gaya - Dhobi section of NH-83
83
127.2
1027
JICA ODA
Oct 2014
IL&FS Engineering and Construction Company Ltd-Indian


-
Under Implementation
3
Four Laning of Madurai - Ramanathapuram (km 5. to km 81) and Two laning with PS km 81 to km 120
49
115
1387.11
NHAI
Apr 2015
May 2015
Nov 2017
KNR Construction Ltd-Indian


-
Under Implementation
4
UP/Haryana border - Yamuna Nagar -Saha- Barwala - Panchkula( PKG - 2)
73
41.79
562.34
NHAI
May 2015
Sadbhav Engineering Ltd-Indian


-
Under Implementation
5
4 laning of Kazhakkottam to Mukkola section of NH-47
47
26.5
845.24
NHAI
May 2015
KNR Constructions Ltd-Indian


-
Under Implementation
6
Four laning of Hospet - Chitradurga
13
120
1388
BOT
Mar 2015
TRIL Roads Pvt Ltd-Indian


-
Under Implementation
7
4 laning of Ambala - Kaithal - Package -2
65
44.5
574.28
NHAI
Mar 2015
Sadbhav Engineering Ltd-Indian


-
Under Implementation
8
4 laning of Ambala - Kaithal - Package -1
65
50.86
602.95
NHAI
Mar 2015
Dilip Buildcon Ltd - Varah Infra Ltd-Indian


-
Under Implementation
9
Four laning of Parwanoo -Solan
22
39.14
934.46
NHAI
Mar 2015
GR Infra Projects Ltd-Indian


-
Under Implementation
10
Two Laning with PS of Nagapattinam - Thanjavur
67
78.53
563.92
NHAI
Mar 2015
Madhucon Projects Ltd-Indian


-
Under Implementation
11
UP/Haryana border - Yamuna Nagar -Saha- Barwala - Panchkula ( PKG - 1)
73
44.57
600.85
NHAI
May 2015
Sadbhav Engineering Ltd-Indian


-
Under Implementation
12
Ludhiana - Talwandi
95
6.02
46.57
NHAI
Nov 2014
M/s Ceigall India Ltd-Indian


-
Under Implementation

NHDP Phase IIIA

13
Gonde-Vadape (Thane)
3
100
579
BOT
Jun 2005
Apr 2006
May 2011
Gammon India Ltd. - Sadbhav - Billimoria Consortium-Indian


Sheladia Associates INC- Artefact Projects Ltd-USA
Completed
14
2/4 Laning of Talchar -Dubari-Chandikhole section of NH-200 from Km 301.89 to Km 427.85 including km 8.5 to Km 14.86 of NH-23
23 &200
132.35
996.37
NHAI
Oct 2014
Corson Corviam Construction S.A-Indian


-
Under Implementation
15
Elevated Highway from Silk board junction to electronic city junction
7
9.98
450
BOT
Dec 2005
Jul 2006
Jan 2010
SOMA - NCC - MAYTAS Consortium-Indian


Renardet S.A - CEG Ltd.-Switzerland - India
Completed
16
Krishnanagar - Berhampore
34
78
702.16
Annuity
Feb 2011
Feb 2012
Feb 2017
SEW Infra.-Indian


YJ Eng. Company Limited in Asso. with Feedback Infra. Services. Pvt. Ltd.-Indian
Under Implementation
17
2 laning with paved shoulder of Karaikudi - Ramanathapuram section of NH-210 including 500 m on SH-35 section of Madurai road
210
80
451.58
NHAI
Oct 2014
Dec 2014
Jun 2017
Transtroy (India ) Ltd-Indian


-
Under Implementation
18
Jalandhar - Amritsar
1
49
263
BOT
May 2005
May 2006
Oct 2010
IVRCL Infrastructure Projects Ltd.-Indian


CES India Ltd.-Indian
Completed
19
Amritsar - Pathankot (Approved Length 101Km)
15
102.42
705
BOT
Jul 2009
May 2010
Dec 2014
IRB-MRM Pvt Ltd.-Indian


ICT in asso. With MC Consulting Eng. & Singhania & Partners-Indian
Under Implementation
20
Chandigarh - Kurali
21
30

-


-
Balance for award
21
Kurali - Kiratpur
21
42.9
309
BOT
Dec 2006
Dec 2007
Jul 2011
BSCPL - C & C Consortium-Indian


ICT Pvt Ltd-Indian
Completed
22
Patna - Bakhtiarpur
30
50.6
574
BOT
Dec 2010
Sep 2011
Nov 2015
BSC-C & C (JV)-Indian


CEG-Indian
Under Implementation
23
4 Laning of Belgaum-Khanpur Section(Km 0.00 to Km 30.00) and 2 Laning with paved sholuders of khanpur-Knt/Goa border.(Km 30.00 to Km 84.120)
4A
81.89
359
BOT
Jul 2010
Mar 2011
Dec 2016
GVR Infra Projects-RMN Infrastructure Ltd-Indian


Lea Associates South Asia Ltd.-Indian
Under Implementation
24
Indore-Khalghat
3
80
472
BOT
Jul 2005
Sep 2006
Sep 2009
Oriental Structural Engineers Pvt. Ltd.- Delhi Brass Consortium-Indian


Sheladia Associates INC - Feedback Turnkey Engineers Pvt. Ltd.-USA -Indian
Completed
25
Khalghat - MP/Maharashtra Border
3
82.8
549
BOT
Oct 2007
Nov 2008
May 2011
Navyuga Engineering Co. Ltd.-Indian


Grontmij/carl Bro in JV with EMA Uniborn India Pvt Ltd-Denmark
Completed
26
Zirakpur - Parwanoo
22
28.69
295
BOT
Feb 2007
Feb 2008
Mar 2012
Jaiprakash Associates-(Himalyan Expressways Pvt. Ltd.)-Indian


Intercontinental Consultants & Technocrafts Pvt. Ltd.-
Completed
27
Barasat - Krishnanagar
34
84
867
Annuity
Feb 2011
Aug 2012
Dec 2017
Madhucon Projects Ltd.-Indian


LEA Associates South Asia Pvt. Ltd.-Indian
Under Implementation
28
Pimpalgaon - Nasik - Gonde
3
60
940
BOT
Jan 2009
Jan 2010
Larsen & Toubro Ltd. - ABL Consortium-Indian


Sheldia-Theme-USA-Indian
Under Implementation
29
Delhi/UP Border to Meerut
58
46

-


-
Balance for award
30
MP/Maharashtra Border-Dhule
3
88.79
835
BOT
Jan 2009
Dec 2009
Mar 2013
Hindustan Construction Company Ltd. -Laing-Sadbhav Consortium-Indian-UK


Wilbur Smith Inc.-USA
Completed
31
Banglore-Hoskote-Mudbagal Section
4
79.724
565
BOT
Feb 2007
Jan 2008
Jun 2011
Lanco Hoskote Highway Pvt. Ltd.-Indian


Zaidun-Leeng SDN.BHD & Artefact Projects(JV)-Malaysian-Indian
Completed
32
Banglore - Neelamangala (Six lane)
4
19.5
445
BOT
Mar 2007
Nov 2007
Dec 2010
Navyuga Engineering Co. Ltd.-Indian


Aarvee Associates in JV with Bonifica-Italy-Indian
Under Implementation
33
Dhule - Pimpalgaon
3
118
556
BOT
Mar 2005
Mar 2006
Mar 2010
IRCON-SOMA Consortium-Indian


Wilbur smith associates Inc.(USA) - WSA Pvt. Ltd. (Indian)-USA - Indian
Completed
34
Amritsar - Wagha border
1
35.93
205.88
Annuity
Aug 2007
Jun 2008
Oct 2010
Rohan Builders Pvt. Ltd. - Rajdeep Buildcon Pvt. Ltd. - IDFC Ltd. Consortium-Indian


-
Completed
35
Patna- Muzzaffarpur
19 & 77
63
671.3
Annuity
Nov 2009
Aug 2010
Mar 2016
Gammon Infrastructure Ltd-Indian


ICT-Indian
Under Implementation
36
Solapur - Maharashtra/ Karnatka Border
13
30

-


-
Balance for award
37
Muzaffarnagar - Haridwar (Approved Length 77 )
58, 72
80
754
BOT
Dec 2009
Sep 2011
Jun 2016
ERA-SIBMOST-Indian - Russian


Nicholas O'Dwyer and SA Infra-
Under Implementation
38
Haridwar - Dehradun (Approved Length 69)
72
39
478
Annuity
Dec 2009
Nov 2011
Sep 2016
ERA - SIBMOST(JV)-Indian - Russian


Intercontinental Consultants & Technocrats Pvt. Ltd.(ICT)-Indian
Under Implementation
39
Meerut-Muzaffarnagar
58
79
359
BOT
Mar 2005
Mar 2006
Aug 2011
Nagarjuna Construction Co. Ltd. - MAYTAS Consortium-Indian


BCEOM- NICE (JV)-French - Indian
Completed
40
Pune - Khed
50
30
127.6
BOT
Aug 2003
Aug 2003
IRB - Madhujaya Consortium-Indian


To be Appointed-
Completed
41
Hyderabad-Yadgiri (Approved Length 30)
202
35.65
388
BOT
Dec 2009
Aug 2010
Dec 2012
Sadbhav Engineering Ltd. (Hyderabad-Yadgiri Tollways Pvt. Ltd.)-Indian


Aarevee Associates Architects Engg. & Consultants Pvt. Ltd.-Indian
Completed
42
Bhubneshwar-Puri(Approved Length 59 Km)
203
67
500.29
BOT
May 2010
Mar 2011
Sep 2015
KSS-Valecha (Bhubneshwar Expressway Pvt. Ltd.)-Indian


CEG Ltd.-Indian
Under Implementation
43
Tirupati -Tiruthani - Chennai(Approved Length 125.5 Km)
205
124.7
571
BOT
Apr 2010
Apr 2011
Mar 2016
Transstroy -OJSC Consortium(JV)-Indian-Russian


Wilbur Smit Associates in Jv with Wilbur Smit Associates Pvt. Ltd.-USA-Indian
Under Implementation
44
Ambala - Zirakpur
21, 22
36
298
BOT
Jun 2005
May 2006
Mar 2009
GMR Energy Ltd. & GMR Infrastruture Ltd. Consortium-Indian


Shela dia Associates INC-USA
Completed
45
End of Durg Bypass - Chattisgarh / Maharashtra Border
6
82.685
464
BOT
Dec 2006
Jan 2008
Dec 2012
Ashoka - IDFC Consortium-Indian


Consulting Engineers Group Ltd-Indian
Completed
46
Hazaribagh-Ranchi
33
73.7
625.07
Annuity
Aug 2009
Aug 2010
May 2015
ITNL-Punj Lloyd Ltd.(JV) (Hazaribagh Ranchi Express way ltd)-Indian


Unihorn India Pvt.Ltd-Indian
Completed
47
Delhi - Hissar (Delhi Portion)
10
20

-


-
Balance for award
48
Pondicherry - Tindivanam
66
38.61
285
BOT
Mar 2007
Jan 2008
Dec 2011
Maytas - NCC Consortium-Indian


Louis Berger-USA
Completed
49
Trichy - Karur
67
79.7
516
BOT
Mar 2007
Jan 2008
Reliance Energy Limited-Indian


WSA Wilbar Smith Associates-USA
Under Implementation
50
Guna Bypass
3
14
46
BOT
Feb 2005
Jan 2006
Dec 2007
Guna Infrastructure Ltd.-Indian


Aarvee Associates-Indian
Completed
51
Kondhali - Telegaon
6
50
212
BOT
Aug 2005
Sep 2006
Mar 2009
Oriental Structural Engineers Pvt. Ltd.- Delhi Brass Consortium-Indian


Consulting Engineers Group Ltd - Roughton International (JV)-Indian - UK
Completed
52
Bijapur - Hungund Section (Approved Length 194 Km)
13
97.22
748
BOT
Feb 2010
Sep 2010
Apr 2012
SEL-MCL Consortium-Indian


-
Completed
53
Panipat - Rohtak(Approved Length 73 Km)
71A
80.858
807
BOT
Jan 2010
Apr 2011
Jan 2014
Sadbhav Engineering Ltd-Indian


-
Completed
54
Rohtak - Bawal(Approved Length 97 Km)
71
83.65
650
BOT
Feb 2010
May 2011
Mar 2016
JMC-SREI(JV)-Indian


-
Under Implementation
55
Parwanoo - Shimla
22
103

-


-
Balance for award
56
Panikholi-Rimoli (Approved Length 106 Km)
215
163
1410
BOT
Aug 2011
May 2013
Jun 2016
Gayatri Projects Ltd.-Indian


Sai Consulting Engg. Pvt. Ltd.-Indian
Under Implementation
57
Rimoli - Roxy - Rajamunda(Approved Length 163Km)
215
96
586
BOT
Apr 2010
Jul 2011
Dec 2016
MBL-SREI-Indian


-
Under Implementation
58
Reengus - Sikar
11
43.887
333.51
Annuity
Mar 2011
Mar 2012
Dec 2015
G.R.Infraprojects Ltd.-Indian


URS Scottwilson India Pvt Ltd-Indian
Under Implementation
59
Agra - Bharatpur
11
45
195
BOT
Jul 2005
Sep 2006
Jun 2009
Oriental Structural Engineers Pvt. Ltd.- Delhi Brass Consortium-Indian


LBG Inc-USA
Completed
60
Bharatpur-Mahua
11
57
250
BOT
Mar 2005
Apr 2006
Mar 2009
Madhucon Projects Ltd. - SREI-Indian


Aarvee Associates-Indian
Completed
61
Mahua-Jaipur
11
108
483
BOT
Mar 2005
Mar 2006
Sep 2009
JMTPL(I) Corporation Project-Malaysian


ICT Pvt Ltd-Indian
Completed
62
Jaipur-Reengus(Approved Length 52.65 Km )
11
54
267.81
BOT
Oct 2009
Aug 2010
Sep 2015
RIL-AAA- JTEG Consortium-Indian-China


M/S Grontmij Carl Bro (Denmark) in JV with SAI Consulting Engineers Pvt. Lt-Denmark-Indian
Under Implementation
63
Bhopal - Bareli
12
297

-


-
Balance for award
64
Jaipur-Tonk - Deoli(Approved Length 148.77 Km )
12
148.92
792.06
BOT
Oct 2009
Jun 2010
Jun 2015
IRB-MRM Consortium-Indian


M/S Aarvee Associates Architects, Engineers & Constt. Pvt. Ltd-Indian
Under Implementation
65
Kundapur-Surathkal & Mangalore-KNT/Kerala Border
17
90
671
BOT
Nov 2009
Sep 2010
Dec 2015
Navayuga - KPCL Consortium-Indian


Aarvee Associates Architect Engineers and Consultants Pvt. Ltd.-Indian
Under Implementation
66
Sitapur - Lucknow
24
75
322
BOT
Aug 2005
Jun 2006
Jan 2012
Apollo(UK) - JLI(UK) - DSC(Indian) - LOR(UK) Consortium-UK - Indian JV


Wilbur smith associates Inc.(USA) - WSA Pvt. Ltd. (Indian)-USA - Indian
Completed
67
Trichy - Dindigul
45
88.273
576
BOT
Mar 2007
Jan 2008
Jan 2012
Reliance Energy Limited-Indian


Zaidung-Leeng SDN.BND-Artefact Projects Ltd(JV)-Malaysian-Indian
Completed
68
Delhi/Haryana Border to Rohtak
10
63.49
486
BOT
Jul 2007
May 2008
Jul 2015
KCT - ERA consortium-Indian


ICT Pvt Ltd-Indian
Under Implementation
69
Aurang - Raipur
6
43.485
190
BOT
Mar 2005
Apr 2006
Jun 2015
Apollo(UK) - JLI(UK) - DSC(Indian) - LOR(UK) Consortium-UK - Indian JV


Renardet S.A - Feedback Turnkey Engineers-Switzerland-Indian
Under Implementation
70
Deoli - Kota
12
83
593
BOT
Apr 2010
Jan 2011
Apr 2016
GVK Development Projects Pvt Ltd-Indian


Scott Wilson Ltd-Scott Wilson India(JV)-UK-Indian
Under Implementation
71
Karaikudi - Ramanathapuram
210
100

-


-
Balance for award
72
Trivendrum -Kerala/TN Border
47
29

-


-
Balance for award
73
Kerala/TN Border - Kanyakumari
47
56

-


-
Balance for award
74
Devihalli-Hassan(Approved Length 73 Km)
48
77.23
453
BOT
Apr 2010
Dec 2010
Jul 2015
Larsen & Toubro Ltd.-Indian


Lea Associates South Asia Pvt . Ltd.-Indian
Under Implementation
75
Neelamangala Junction on NH 4 with NH 48 to Devihalli
48
81
441
BOT
Apr 2007
Jan 2008
May 2012
Lanco Devihalli Highways Pvt. Ltd.-Indian


Consulting Engineers Group Ltd.-Indian
Completed
76
Barasat - Bangaon
35
60

-


-
Balance for award
77
2-Laning of Krishnagiri-Tindivanam (Approved Length 170 Km.)
66
176.51
624
Annuity
May 2011
Apr 2012
Mar 2016
Transstroy (I) Ltd. - Corporation Transstroy OJSC Consortium-Indian - Russian


-
Under Implementation
78
Two Laning of Trichy - Karaikudi and Trichy Bypass(Approved Length 100 Km)
210 & 67
110.372
374
Annuity
May 2010
May 2011
Dec 2015
Transstroy Ltd-OJSC Consortium-Indian-Russian


Euroestudios, S.L. Spain In associated with Theme Engg. Services Pvt.Ltd.-Spain-Indian
Under Implementation
79
Tanjore - Trichy
67
56.49
280
BOT
Feb 2006
Dec 2006
May 2015
Madhucon Projects Ltd.-Indian


Louis Berger-USA
Completed
80
Salem-Ulundrupet (BOT-1/TN-06)
68
136.357
941
BOT
Mar 2007
Jan 2008
Oct 2013
Reliance Energy Limited-Indian


Technital SPA-Italy
Completed
81
Kandla - Mundra Port(Approved Length 73 Km)
8A
71.4
953.88
BOT
Jan 2010
Jan 2011
Dec 2015
Reliance Infra Projects Ltd.-Indian


Dorsch Gruppe-Indian
Under Implementation
82
Madurai-Arupukottai-Tuticorin
45B
128.16
629
BOT
Feb 2006
Jan 2007
Dec 2011
Madhucon Projects Ltd. - SREI - Madhucon granites Ltd (JV)-Indian


Louis Berger-USA
Completed
83
Hungund-Hospet (Approved Length 194 Km)
13
97.89
946
BOT
Feb 2010
Sep 2010
Mar 2014
GMR-OSE Consortium-Indian


SMEC-Indian
Under Implementation
84
Hyderabad-Vijayawada
9
181.63
1740
BOT
May 2009
Apr 2010
Mar 2013
GMR-Punj LLOYD Consortium(GMR-Hyderabad Vijayawada Expressway Pvt. Ltd.)-Indian


ICT Pvt. Limited-Indian
Completed
85
Chattisgarh / Maharashtra Border - Wainganga Bridge
6
80
424
BOT
Dec 2006
Mar 2008
Sep 2010
Ashoka - IDFC Consortium-Indian


Zaidun-Leeng SDN.BHD-Artefact Projects Ltd(JV)-Malaysian-Indian
Completed
86
Six Laning of Bangalore-Hosur Section of NH-7
7
14.38
110
NHAI
Apr 2007
Apr 2007
Apr 2010
GVR Construction Pvt. Ltd. Chennai-Indian


Louis Burger Inc.-USA
Completed
87
Nagpur-Wainganga Bridge (Approved Length - 60 Km)
6
45.43
484.19
BOT
May 2011
Apr 2012
Mar 2016
JMC Projects India Ltd.-Indian


Artefact Projects Ltd.-Indian
Under Implementation
88
Nagpur - kondhali
6
40
168
BOT
Sep 2005
Jun 2006
Atlanta - SREI Consortium (JV)-Indian


Aarvee Associates-Indian
Under Implementation

NHDP Phase IIIB

89
Talegaon-Amravat(Approved Length 58Km)
6
67.8
567
BOT
Aug 2009
Nov 2009
IRB-MRM Consortium-Indian


Wilbur Smith Associates Pvt. Ltd.-Indian
Under Implementation
90
4 Laning of Godhara to Gujarat /MP Border(Approved Length 210 Km)
59
87.285
785.5
BOT
Jan 2010
Mar 2011
BSPCL Ltd-Indian


Intercontinental Consultants and Technocrats Pvt. Ltd.-Indian
Under Implementation
91
4 Laning of Ahmedabad to Godhara (Approved Length 210 Km)
59
117.6
1008.5
BOT
Jan 2010
Dec 2010
Jul 2015
ESSEL Infra & CR-18 Consortium-Indian-china


Egis International-Egis India Consulting Engg. Pvt. Ltd.-France-Indian
Under Implementation
92
Madurai-Ramnathpuram-Rameshwaram-Dhanuskodi
49
186

-


-
Balance for award
93
Ghaziabad-Aligarh (Approved Length 106 )
91
126
1141
BOT
Dec 2009
Feb 2011
Aug 2015
SREI - PNC - GALFAR Consortium-Indian - Dubai


SNC-Lavalin Infrastructure Pvt. Ltd.-Canada
Under Implementation
94
Silchar - Assam/Mizoram Border
54
50

-


-
Balance for award
95
Kishangarh-Ajmer-Beawar
8
93.56
795
BOT
Apr 2009
Nov 2009
Aug 2015
Isolux-Soma Consortium-Spain-Indian


Louis Barger Group, Inc USA-USA
Under Implementation
96
Indore-Jhabua-Gujrat/MP (Approved Length 168)
59
155.15
1175
BOT
Dec 2009
Oct 2010
Dec 2015
IVRCL Infrastructure Projects Ltd.-Indian


EURO Studios Feedback Venture-
Under Implementation
97
Jhansi-Khajuraho
75
100

-


East Consult-LRP Consultants Consortium Pvt. Ltd.-Nepal
Balance for award
98
Gujarat/Maharashtra Border-Surat - Hazira Port Section
6
132.9
1509.1
BOT
Feb 2009
Mar 2010
Nov 2015
Isolux-Soma Consortium (JV)-Spain-Indian


Sheladia Association Inc.-Multimedia Consultant Pvt Ltd-USA-Indian
Under Implementation
99
Kalamboli-Mumbra(6 laning)
4
20

-


-
Balance for award
100
4 Laning of Obedullaganj-Betul Section
69
125
912
BOT
Feb 2012
Feb 2014
Aug 2016
Transstroy (India) Ltd.-Indian


M/s CEG-Indian
Under Implementation
101
Obaidullaganj-Bheembetka
69
13

-


-
Balance for award
102
Four lanning of Ludhiyana- Talwandi section
95
78
479
BOT
Dec 2010
Mar 2012
Nov 2015
Essel Infra Projects Ltd.- Pan Indian Networks Ltd.-Indian


Louis Berger Group, Inc in Asso. With LBC Pvt. Ltd.-USA
Under Implementation
103
Pondicherry - TN/Pondicherry Border
66
4

-


-
Balance for award
104
4-Laning of Solapur - Maharashtra/ Karnatka Section
9
100.06
923.04
BOT
Dec 2011
Jun 2014
Nov 2016
Coastal-SREI Consortium-Indian


Artefact Projects Ltd.-Indian
Under Implementation
105
4-Laning of Rohtak-Jind (Approved Length 45 Km)
71
48.6
283.25
BOT
Dec 2011
Oct 2013
Oct 2015
Vijai Infrastructure Ltd.-Indian


-
Under Implementation
106
up to Delhi/UP Border
1 & 24
8

-


-
Balance for award
107
4 Laning of Raiganj-Dalkola
34
50
580.43
BOT
Feb 2010
Feb 2011
May 2017
Hindustan Construction Company Ltd.-Indian


URS Scott Wilson Indian Pvt. Ltd. In Associate with Rodic Consultant P Ltd.-Indian
Under Implementation
108
4 Laning of Faraka-Raiganj
34
103
1078.84
BOT
Feb 2010
Feb 2011
Aug 2016
Hindustan Construction Company Ltd.-Indian


URS Scott Wilson Indian Pvt. Ltd. In Associate with Rodic Consultant P Ltd.-Indian
Under Implementation
109
4 Laning of Brahampore-Faraka
34
103
998.79
BOT
Feb 2010
Feb 2011
Jul 2017
Hindustan Construction Company Ltd.-Indian


URS Scott Wilson Indian Pvt. Ltd. In Associate with Rodic Consultant P Ltd.-Indian
Under Implementation
110
Four Laning of Kiratpur-Ner Chowk Section
21
84.32
1916.79
BOT
Feb 2012
Nov 2013
Nov 2016
IL & FS Transportation Networks Ltd.-Indian


Getinsa Ingenieria S.L.Spain in Asso. with Segmental Cons. & Supp. Pvt. Ltd-Spain-Indian
Under Implementation
111
MH/ KNT Border Sangareddy
9
145
1266.6
BOT
Nov 2011
Apr 2014
Sep 2016
L&T Infrasructure Developement Projects Ltd-Indian


CDM Smith JV with Willbur Smith-Indian
Under Implementation
112
Sambalpur-Baragarh-Chattisgarh/Orrisa Border
6
88
909
BOT
May 2010
Nov 2011
Jul 2015
Ashoka Buildcon Ltd-(Ashoka Sambalpur Baragarh Expressway Pvt. Ltd.)-Indian


ICT-Indian
Under Implementation
113
4 Laning of Chappra-Hajipur(Approved Length 153 Km)
19
65
575
Annuity
May 2010
Jan 2011
Dec 2015
Madhucon Projects Ltd-Indian


Stanly Cunsultant Inc-USA
Under Implementation
114
4-Laning of Rohtak - Hissar Section
10
98.81
959.25
BOT
Mar 2013
Dec 2013
Jun 2016
Sadbhav Engg. Limited-Indian


-
Under Implementation
115
Pune-Sholapur Pkg-II(Approved Length I & II 170 Km)
9
105
835
BOT
Aug 2009
Sep 2011
Nov 2015
IL & FS Transportation Network Ltd-Indian


ICT Pvt. Ltd.-Indian
Under Implementation
116
Baihata Chariali- Banderdewa
52
314

-


-
Balance for award
117
2-Laning with PS khagaria - Purnea
31
140
664
Annuity
Feb 2011
May 2011
Oct 2015
Punj Lloyd Infrastructure Ltd.-Indian


Bloom Companies LLC-USA
Under Implementation
118
2-Laning with PS Motihari-Raxaul (Approved Length 67 Km)
28A
68.79
375.09
BOT
Jan 2011
Oct 2011
Mar 2016
Tantia-Jiangsu (JV)-Indian-China (JV)


Frischmann Prabhu (India) Pvt. Ltd.-Indian
Under Implementation
119
Doboka-Assam/Nagaland Border
36
124

-


-
Balance for award
120
Shillong (Excluding Shillong By Pass ) - Jowai
44
27

-


-
Balance for award
121
Assam Mizoram Border to Aizawl
54
140

-


-
Balance for award
122
Nagaland /Manipur Border -Imphal
39
111

-


-
Balance for award
123
Itanagar-Arunachal Pradesh/Assam Border
52A
22

-


-
Balance for award
124
4-Laning of Punjab/Haryana Border-Jind
71
68
438.75
BOT
Mar 2012
Mar 2014
Sep 2016
Unity Infraprojects Ltd.-Indian


-
Under Implementation
125
Ranchi - Rargaon - Jamshedpur
33
163.5
1479
Annuity
Mar 2011
Dec 2012
Dec 2016
Madhucon Projects Ltd.-Indian


Aarvee-Indian
Under Implementation
126
Raipur-Simga
200
28

-


-
Balance for award
127
4 Laning of Mulbagal - Karnataka / AP border-Approved Length (11 Km)
4
22.18
141.11
BOT
Mar 2012
May 2013
Jul 2015
J.S.R. Construction Pvt Ltd-Indian


Artefact-Indian
Under Implementation
128
Beawar-Pali-Pindwara (Approved Length - 246 Km)
14
244.12
2388
BOT
May 2011
Dec 2011
Nov 2015
L&T Infrastructure Development Projects Ltd.-Indian


Sheladia-Aarvee-USA-Indian
Under Implementation
129
Assam/Meghalaya Border - Assam/Tripura Border
44
116

-


-
Balance for award
130
Panvel-Indapur
17
84
942.69
BOT
Oct 2010
Dec 2011
Dec 2015
Supreme Infrastructure India Ltd.-Mahavir Road & Infrastructure Pvt. Ltd.-China State Construction Engg. Hongkong Ltd.-Indian-China


Yongma Engg.Co.Ltd. In Asso. With Feedback Venture Pvt. Ltd.-Korea-Indian
Under Implementation
131
2 Laning of Muzaffarpur - Sonbarsa(Approved Length 89 Km)
77
86
511.54
Annuity
Jul 2010
May 2011
Dec 2015
BSCPL-C&C(JV)-Indian


ICT Pvt Ltd.-Indian
Under Implementation
132
Kudapa-Mydukur-Kurnool
18
188.752
1585
BOT
Feb 2009
Nov 2010
Dec 2015
KMC Construction Ltd. - IVRCL Consortium-Indian


Aarevee Associates Architects-Indian
Under Implementation
133
Muradabad-Bareily (Approved Length 112)
24
121
1267
BOT
Dec 2009
Apr 2010
Jul 2015
IL & FS Transportation Ltd.-Indian


LBG-USA
Under Implementation
134
2 Laning of Mokama-Munger(Approved Length 70 Km)
80
69.27
351.54
Annuity
May 2010
May 2011
Jul 2015
BSCPL -C & C Consortium-Indian


Nicholoso'-Dwyer-Upham Infrastructure-Irland-Indian(JV)
Under Implementation
135
Bareily - Sitapur(Approved Length 134 Km)
24
151.2
1046
BOT
Apr 2010
Mar 2011
Dec 2016
ERA-SIBMOST-Indian-Russian


Intercontinental Consultant Pvt. Ltd.-Indian
Under Implementation
136
Kurnud-Dhamtari
43
23

-


-
Balance for award
137
Pune-Sholapur Pkg-I(Approved Length Pkg I & II 170 Km)
9
110.05
1110
BOT
Feb 2009
Nov 2009
Apr 2015
Navinya Buildcon-Atlantia Spa(JV)-Indian-Italy


Renardet S.A.-Switzerland
Under Implementation
138
4 laning of Jetpur-Somnath section of NH-8D (approved length 127.6)
8D
123.45
828
BOT
Sep 2010
Mar 2012
Nov 2015
IDFC-PLUS Expessway Berhad Consortium-Indian-Malaysian (JV)


-
Under Implementation
139
2 Laning of Dindigul-Perigulam-Theni-Kumili
220
134
485
Annuity
May 2010
Sep 2011
Dec 2015
Transstroy-OJSC Consortium Ltd-Indian-Russian


ICT Private Limited-Indian
Under Implementation
140
Kohima-Nagaland/Manipur Border
39
28

-


-
Balance for award
141
Banderdewa - Assam/AP Border
52A
9

-


-
Balance for award