Projects Under Implementation as on   31st July 2016

 NHDP Wise Details

S.no
Stretch

NH No Length(Km)
On North South & East West Corridor Phase II

East-West

1
Balance work of 4 laning of Gorakpur -Gopalganj 28 41
2
Nalbari to Bijni (AS-6) 31 25
3
Nalbari to Bijni (AS-7) 31 27.3
4
Brahmputra Bridge (AS-28) 31 5
5
Guwahati to Nalbari (AS-4) 31 28
6
Construction of Islampur By pass 31 10.31
7
Bijni to Assam/WB Border (AS-11) 31C 30
8
Bijni to Assam/WB Border (AS-10) 31C 33
9
Bijni to Assam/WB Border (AS-12) 31C 30
10
4 Laning of NH-31D from Ghoshpukur - Salsalabari ( km 0.00 to Km . 83.785) 31-D 83.785
11
Dharamtul to Sonapur (AS-20) 37 22
12
Sonapur to Guwahati (AS-3) 37 19
13
Nagaon to Dharmatul (AS-2) 37 25
14
Maibang to Lumding (AS-26) 54 23
15
Harangajo to Maibang (AS-21) 54 26
16
Harangajo to Maibang (AS-22) 54 24
17
Maibang to Lumding (AS-27) 54 21
18
Maibang to Lumding (AS-25) 54 28
19
Maibang to Lumding (AS-24) 54 15
20
Harangajo to Maibang (AS-23) 54 16
21
Forbesganj-Simrahi (BR-3) 57 34.87
22
Chambal Bridge (RJ-5) 76 1.4

North-South

23
Four laning of Udhambur - Ramban section of NH-1A 1A 40.17
24
Four laning of Ramban - Banihal section of NH-1A 1A 32.1
25
Chenani-Nashri 1A 12
26
Quazigund-Banihal 1A 15.25
27
Jammu - Udhampur 1A 65
28
Srinagar to Banihal 1A 67.76
29
New 4 laning Agra Bypass (NS-1/UP-1) 2,3 32.8
30
Six lanning of Vadakkancherry - Thrissure section 47 30
31
Chengapalli to Coimbatore Bypass and End of Coimbatore Bypass to TN/Kerala Border 47 54.83
32
Balance work of four laning of Nagpur - Hyderabad section of NH-7( NS-60) 7 29
33
Balance work of four laning of Nagpur - Hyderbad section of NH-7(NS-62) 7 22
34
Four laning from MP/Maharashtra border to Nagpur I/C Kamptee Kanoon and Nagpur bypass 7 95
35
Gwalior - Jhansi 75 80
On Port Connectivity

Port Connectivity

36
6/8 Laning of Road port connectivity JNPT phase II -Construction of NH-348 - PKG3 348 11.09
37
Construction of NH-4B from km.21.200 to Km.27.270( D to e section) and from km.0.000 to Km.4.492 ( D to g section) of JNPT Phase -II (PKG-IV) 4B 10.56
38
Construction of Karalphata Interchange from 3.600 to km 6.073 of NH4B & from 5.300 to km 7.422 ( Old SH -54) Pkg-1 4B & 348 10.59
39
Construction of Gavanphata Interchange from 14.740 to Km 15.894 ( Old SH -54) Pkg-2 4B & 348 18.27
40
Four laning of Balance connectivity road from Visakhapatnam Port to NH5 5 4.15
41
Development of Adiquate Road Connectivity to Chennai -Ennore Port Connectivity SR 30.2
Other Phase II Projects

42
Jalandhar - Amritsar 1 20
NHDP Phase III
43
Four laning of Hospet - Chitradurga 13 120
44
Four laning of Parwanoo -Solan 22 39.14
45
Four laning of Patna to Koilwar 30 33.25
46
Four laning of Koilwar to Bhojpur 30 &84 43.85
47
Four of Simaria - Khagaria section of NH-31 31 60.23
48
Four laning of Bakhtiyarpur - Mokama section of NH-31 31 44.6
49
4 laning of Mahulia - Baharagora - JH/WB border 33 & 6 71.61
50
Two laning with PS of Jowai -Mehalaya /Assam border section of NH-44 44 102.55
51
4 laning of Kazhakkottam to Mukkola section of NH-47 47 26.5
52
4 laning of Mukkola Jn to Kerala / TN border of NH-47 47 16.2
53
Four laning of TN/Kerala border to Villukuri 47 27.25
54
Four laning of Villukuri to Kanyakumar section of NH-47 & Nagarcoil to Kavalkinaru section of Nh-47B 47 &47-B 42.7
55
Four Laning of Madurai - Ramanathapuram (km 5. to km 81) and Two laning with PS km 81 to km 120 49 115
56
Four Laning of Forbesganj - Jogbani 57A 9
NHDP PHASE III
57
4 laning of Ambala - Kaithal - Package -1 65 50.86
58
4 laning of Ambala - Kaithal - Package -2 65 44.5
59
Two Laning with PS of Nagapattinam - Thanjavur 67 78.53
NHDP Phase III
60
UP/Haryana border - Yamuna Nagar -Saha- Barwala - Panchkula ( PKG - 1) 73 44.57
61
UP/Haryana border - Yamuna Nagar -Saha- Barwala - Panchkula( PKG - 2) 73 41.79
62
Four laning of Patna - Gaya - Dhobi section of NH-83 83 127.2
63
Four laning of Bhojpur to Buxar 84 47.9
64
Two laning with PS of Chhapra -Gopalganj 85 94.25
65
Four laning of Vijayawada - Machlipatnam 9 64.61
66
Ludhiana - Talwandi 95 6.02

NHDP Phase IIIA

67
Delhi/Haryana Border to Rohtak 10 63.49
68
Deoli - Kota 12 83
69
Kundapur-Surathkal & Mangalore-KNT/Kerala Border 17 90
70
Patna- Muzzaffarpur 19 & 77 63
71
Bhubneshwar-Puri(Approved Length 59 Km) 203 67
72
Tirupati -Tiruthani - Chennai(Approved Length 125.5 Km) 205 124.7
73
2 laning with paved shoulder of Karaikudi - Ramanathapuram section of NH-210 including 500 m on SH-35 section of Madurai road 210 80
74
Two Laning of Trichy - Karaikudi and Trichy Bypass(Approved Length 100 Km) 210 & 67 110.372
75
Panikholi-Rimoli (Approved Length 106 Km) 215 163
76
Rimoli - Roxy - Rajamunda(Approved Length 163Km) 215 96
77
2/4 Laning of Talchar -Dubari-Chandikhole section of NH-200 from Km 301.89 to Km 427.85 including km 8.5 to Km 14.86 of NH-23 23 &200 132.35
78
Pimpalgaon - Nasik - Gonde 3 60
79
Patna - Bakhtiarpur 30 50.6
80
Barasat - Krishnanagar 34 84
81
Krishnanagar - Berhampore 34 78
82
4 Laning of Belgaum-Khanpur Section(Km 0.00 to Km 30.00) and 2 Laning with paved sholuders of khanpur-Knt/Goa border.(Km 30.00 to Km 84.120) 4A 81.89
83
Muzaffarnagar - Haridwar (Approved Length 77 ) 58, 72 80
84
Nagpur - kondhali 6 40.7
85
2-Laning of Krishnagiri-Tindivanam (Approved Length 170 Km.) 66 176.51
86
Trichy - Karur 67 79.7
87
Rohtak - Bawal(Approved Length 97 Km) 71 83.66
88
Haridwar - Dehradun (Approved Length 69) 72 39
89
Kandla - Mundra Port(Approved Length 73 Km) 8A 71.4

90
Panvel-Indapur 17 84
91
Kudapa-Mydukur-Kurnool 18 188.752
92
4 Laning of Chappra-Hajipur(Approved Length 153 Km) 19 65
93
Four Laning of Kiratpur-Ner Chowk Section 21 84.32
94
2 Laning of Dindigul-Perigulam-Theni-Kumili 220 134
95
Muradabad-Bareily (Approved Length 112) 24 121.3
96
Bareily - Sitapur(Approved Length 134 Km) 24 151.2
97
2-Laning with PS Motihari-Raxaul (Approved Length 67 Km) 28A 68.79
98
2-Laning with PS khagaria - Purnea 31 140
99
Ranchi - Rargaon - Jamshedpur 33 163.5
100
4 Laning of Raiganj-Dalkola 34 50
101
4 Laning of Faraka-Raiganj 34 103
102
4 Laning of Brahampore-Faraka 34 103
103
4 Laning of Ahmedabad to Godhara (Approved Length 210 Km) 59 117.6
104
Indore-Jhabua-Gujrat/MP (Approved Length 168) 59 155.15
105
Gujarat/Maharashtra Border-Surat - Hazira Port Section 6 132.9
106
Talegaon-Amravat(Approved Length 58Km) 6 67.8
107
4 Laning of Obedullaganj-Betul Section 69 125
108
4-Laning of Rohtak-Jind (Approved Length 45 Km) 71 48.6
109
2 Laning of Muzaffarpur - Sonbarsa(Approved Length 89 Km) 77 86
110
2 Laning of Mokama-Munger(Approved Length 70 Km) 80 69.27
111
4 laning of Jetpur-Somnath section of NH-8D (approved length 127.6) 8D 123.45
112
MH/ KNT Border Sangareddy 9 145
113
4-Laning of Solapur - Maharashtra/ Karnatka Section 9 100.06
114
Ghaziabad-Aligarh (Approved Length 106 ) 91 126
115
Four lanning of Ludhiyana- Talwandi section 95 78
NHDP Phase V

NHDP Phase V

116
Panipat - Jalandhar (Six lane) 1 291
117
Six-laning of Barwa Adda-Panagarh 2 122.88
118
Delhi - Agra(Approved Length 180.3 Km) 2 179.5
119
6 laning of Agra - Etawah bypass 2 124.5
120
Varanasi-Aurangabad 2 192.4
121
Etawah -Chakeri (Kanpur) 2 160.2
122
Four laning of Chadigarh - Kharar 21 & 95 10.18
123
Indore-Dewas(Approved Length 55 Km) 3 45.05
124
Pune Satara(Approved Length 145) 4 140.35
125
Six Laning of Krishnagiri-walajhapet section 46 148.3
126
Walajapet-Poonamalee 46 93
127
Six Laning of Chandikhol-Jagatpur-Bhubaneswar(Approved Length 61 Km) 5 67
128
Vijayawada-Gundugolanu Section 5 103.59
129
Chennai - Tada (Six lane) 5 43.4
130
Six Laning of Nellore-Chilkaluripet 5 183.52
131
6-Laning of Dhankuni-Khargpur Section 6 111.4
132
Six Laning of Hosur-Krishnagiri 7 59.87
133
six laning of greenfield proposed Udaipur Bypass 8 23.88
134
Six Laning of Kamrej - Chalthan 8 16.25
135
Vadodara-Surat Section 8 6.74
136
Ahmedabad to Vadodara Section 8 102.3
137
Gurgaon - Kotputli - Jaipur (Six lane) 8 225.6
138
Surat - Dahisar (Six lane) 8 239
139
Samaikhiali-Gandhidham 8A 56.16
NHDP Phase IV

140
Four laning of Rampur - Kathgodam ( PKG-I) 87 43
141
Four laning of Rampur - Kathgodam ( PKG-II) 87 45
142
Four Laning of Hisar - Dabwali section with PS - Package -2 10 87.66
143
Four Laning of Hisar - Dabwali section with PS - Package -I 10 57
144
Two laning with PS of Chhapra -Rewaghat - Muzaffarpur 102 73
145
Jodhpur - Barmer section of Package -I 112 85.61
146
Jodhpur - Barmer section of Package -II 112 74.1
147
Four laning of Bar - Bilara - Jodhpur 112 111
148
Padi - Dahod 113 85.58
149
Two lane with paved shoulders of Jodhpur - Pokaran section of NH-114 ( New NH No -50) 114 139.33
150
2 laning with PS of Manoharpur -Dausa section of NH-11A 11A 62.31
151
Four laning / Two Laning with PS of Dausa - Lalsot - Kauthun section of NH-11A 11A Extn 83.45
152
Two laning with Paved shoulder of KarauIi - Dholpur 11B 100.9
153
Two Laning with PS of Uncha Nagla - Khanuwara - Roppas -Dholpur 123 75.08
154
2 laning with paved shoulder of Sitarganj - Tanakur section of NH-125 125 52
155
2 Laning with PS of Gulabpura - Uniara 148-D 203.97
156
Bikaner - Phalodi section to Four laning from km.4.200 to km 55.25 and Two-lane paved shoulder from 55.25 to km.163.500 15 160.3
157
Jaisalmer - Barmer 15 131.41
158
Phalodi -Jaisalmer section of NH-15 to two/four lane with PS 15 160.45
159
Two laning with paved shoulder Barmer - Sanchor - Gujarat boder ( up to Gandhav Bridge) section of NH-15 15 106.3
160
Four laning of Yadgiri - Warangal 163 99.1
161
4-Laning of Goa/Karnataka Border-Kundapur Section 17 187.24
162
Four laning of Simga - Saragaon 200 42.44
163
Four laning of Saragaon - Bilaspur 200 35.49
164
Four / Six laning of Raipur - Simga ( PKG-1) 200 48.58
165
4-Laning of Hoskote-Dobbaspet 207 80.02
166
Two laning with paved shoulderof Kullu - Manali 21 37.34
167
4-Laning of Solapur - Yedishi section of NH-211 211 100
168
Four Laning of Aurangabad - Yedishi 211 190.2
169
Two lane with paved shoulders of Bijapur - Gulbarga - Homnabad - section of NH-218 ( New NH No -50) 218 220.1
170
Thanjavur - Pudukottai section of NH-226 226 55.22
171
Thirumayam - Manamadurai section 226 77.72
172
Two lane with paved shoulders of Chas -Ramgarh section of NH-23 23 78.19
173
4-laning of Ghaghra bridge to Varansi ( Package -I) 233 58.62
174
Four Laning of Ghaghra Bridge to Varanasi (PKG-III) 233 59.07
175
Four Laning of Ghaghra Bridge to Varanasi (PKG-II) 233 59.95
176
Meerut - Bulandshahar 235 61.19
177
2-Laning with paved shoulder of Muzaffarpur - Barauni 28 107.56
178
4- laning of Varanasi - Gorakpur ( PKG-III) 29 65.38
179
4- laning of Varanasi - Gorakpur ( PKG-II) 29 72.15
180
4- laning of Varanasi - Gorakpur ( PKG-IV) 29 65.62
181
Four laning of Varanasi Bypass 29&56 16.55
182
4 Laning of Guna to Biaora 3 93.5
183
Four Laning of Shivpuri - Guna Package - I 3 97.7
184
4 laning of Biaora - Dewas 3 141.26
185
Four laning of Gwalior-Shivpuri 3 125.03
186
Four / 2 Laning with PS of Govindpur ( Raigunj) - Cahs - WB border section of NH-32 32 56.88
187
Widening & strengthening to 2-Lane with PS of Nimbi Jodha-Degana-Merta City Section 458 139.9
188
Four Laning of addahole to Baniwal 48 63.05
189
Four laning of Hasan to Maranahally 48 45.14
190
4 laning of Jharpokharia - Baripada - Baleashwar section of NH-5 5 80.6
191
4-Laning of Khed - Sinnar Section 50 137.946
192
Four laning of Sultanpur to Varanasi (PKG-I) 56 74.53
193
Four laning of Sultanpur to Varanasi (PKG-II) 56 63.36
194
Four laning of Orissa/Chattisgarh Border - Aurang section 6 150.4
195
Four laning with PS Talebani -Smbalpur 6 50.74
196
4 Laning of Baharagora - Singhara 6 111.6
197
4 Laning of Fagne - Mah-Guj Border ( PKG-3) 6 140.79
198
4 Laning of Amravati - Chikhli (PKG-I) 6 194
199
Four laning of Kaithal - Rajasthan border 65 166.25
200
2-Lane with paved shoulder with provision of Capacity Augmentation of Rajasthan Border-Fatehpur-Salasar Section 65 154.141
NHDp Phase IV
201
Salasar - Nagaur section of NH-65 65 119.59
NHDP Phase IV
202
4 Laning of Nagpur Betul 69 176.3
203
Four Laning of Rewa - Katni - Jabalpur - Package -I 7 69.19
204
Four Laning of Rewa - Katni - Jabalpur - Package -IV 7 68.26
205
Four Laning of Rewa - Katni - Jabalpur - Package -II 7 69.07
206
Four Laning of Jabalpur - Lakhnadon 7 80.92
207
4 laning of Chultmalpur - Ganeshpur and Roorkee - Chutmalpur- Gagalheri 72-A &73 53
208
4 laning of Gagalgeri - Saharanpur - Yamunanagar ( UP/ Haryana Border) 73 51
209
4-Laning of Kashipur-Sitarganj Section 74 77.2
210
Four laning of Haridwar - Nagina 74 72
211
2-Laning with PS Sitarganj Bareily Section 74 74.46
212
Four laning of Nagina - Kashipur 74 98.8
213
2-Laning with PS of Bhilwara-Ladpura section 758 67.75
214
4-Laning of Rajsamand-Gangapur-Bhilwara 758 87.25
215
Two laning with PS of Biharaharif -Barbigha - Mokama 82 55
216
Four laning of Mahuva to Kagavadar section of PKG-III 8E 40.02
217
Four laning of Talaja - Mahuva 8E 45.46
218
Four laning of Bhavnagar - Talaja 8E 48.04
219
Four laning of Kagavadar - Una 8E 40.98
220
4 laning of Kodinar to Veraval section of NH-8E 8E 41.74
221
Four laning of Una - Kodinar 8E 40.95
222
Two laning with paved shoulder of Aligarh - Moradabad 93 146
223
2-Laning with PS Raibariely to Allahabad 24B 119
NHDP Phase VI
224
Delhi - Meerut Expreeway (PKG-2) 24 21.92
225
Delhi - Meerut Expreeway (PKG-1) 24 8.716
226
Development of six lane Eastern Peripheral Expressway ( PKG-I) NE-II 22
227
Development of six lane Eastern Peripheral Expressway ( PKG-VI) NE-II 22
228
Development of six lane Eastern Peripheral Expressway ( PKG-V) NE-II 21
229
Development of six lane Eastern Peripheral Expressway ( PKG-IV) NE-II 22
230
Development of six lane Eastern Peripheral Expressway ( PKG-II) NE-II 24.5
231
Development of six lane Eastern Peripheral Expressway ( PKG-III) NE-II 24.5
NHDP Phase VII
232
Construction of 4 Lane Laddowal bypass linking NH-95 with NH-1 17.04
233
Four lane stand alone Rind Road / bypasses for Nagpur City ( PKG-I) 33.5
234
Four lane stand alone Rind Road / bypasses for Nagpur City ( PKG-II) 28.03
235
New 4-Lane Elevated Road from Chennai Port - Maduravoyal 4 19
Others(Misc.)
236
Improvement of Amritsar bypass by construction of additional structure and service roads on NH-1 1 0
237
8 Laning of Mukarba Chowk to Panipat 1 69.84
238
Construction of Flyover at Bahalgarh ch.41.210 and construction of additional 2-lane bridge near Rasoi Ch.32.28 on NH-1 in the state of Haryana 1 0
239
Four laning of Kharar - Kurali section of NH-21 21 14.13
240
2-laning with paved shoulders of Raebareli - Banda section of NH-232 232 133.28
241
2-laning with paved shoulders of Tanda -Raebareli 232 155.9
242
Bhatinda-Suratgarh (ROB) 32-B 0
Others ( Misc.)
243
Construction of Flyover at Km.544.650 including ROB ,Service Roads ,Footpath for RCC drains on urban link to Nagpur -Raipur road 6 6.94
Port Connectivity

Port Connectivity

244
Construction of ROB -flyover at Ranichak , Haldia 41 1.39
SARDP

245
Jorbat-Barapani 40 61.8