GOLDEN QUARDRILATERAL:Overall Progress Corridor Wise Including Completed Length as on 31st January, 2009
 
All lengths in Kms.
CORRIDOR AND ITS TOTAL LENGTH
(in km)
Cumulative length completed in km (in %)
Cum % progress of contracts under implementation
By end of last month
By end of month under report
By end of last month
By end of month under report
DELHI-MUMBAI
[1419 KM]
1419
(100%)
1419
(100%)
-
-
MUMBAI-CHENNAI
[1290 KM]
1263
(97.90%)
1263
(97.90%)
47.55%
(for 164 km)
49.58%
(for 164km)
1585
(94.12%)
1591
(94.48%)
50.24%
(for 197 km)
50.64%
(for 197 km)
DELHI-KOLKATA
[1453 KM]
1436
(98.83%)
1440
(99.10%)
88.30%
(for 366 km)
89.82%
(for 366 km)
TOTAL GQ
 [5846 KM]
5704
(97.57%)
5713 
(97.72%)
79.35%
(for 727 km)
80.71%
(for 727 km)
 