GOLDEN QUARDRILATERAL:Overall Progress Corridor Wise Including Completed Length as on 30th November 2011
All lengths in Kms.
CORRIDOR AND ITS TOTAL LENGTH
(in km)
Cumulative length completed in km (in %)
Cum % progress of contracts under implementation
By end of last month
By end of month under report
By end of last month
By end of month under report
DELHI-MUMBAI
[1419 KM]
1419
(100%)
1419
(100%)
-
-
MUMBAI-CHENNAI
[1290 KM]
1290
(100%)
1290
(100%)
75.32%
(for 164km)
75.92%
(for 164km)
KOLKATA- CHENNAI
[1684 KM]
1666
(98.93%)
1667
(98.93%)
74.26%
(for 197 km)
75.19%
(for 197 km)
DELHI-KOLKATA
[1453 KM]
1453
(100%)
1453
(100%)
99.44%
(for 51 km)
99.44%
(for 51 km)
TOTAL GQ
[5846 KM]
5827
(99.67%)
5829
(99.71%)
77.98%
(for 412 km)
78.46%
(for 412 km)