GOLDEN QUARDRILATERAL:Overall Progress Corridor Wise Including Completed Length as on 31st January, 2010
 
All lengths in Kms.
CORRIDOR AND ITS TOTAL LENGTH
(in km)
Cumulative length completed in km (in %)
Cum % progress of contracts under implementation
By end of last month
By end of month under report
By end of last month
By end of month under report
DELHI-MUMBAI
[1419 KM]
1419
(100%)
1419
(100%)
-
-
MUMBAI-CHENNAI
[1290 KM]
1270
(98.45%)
1273
(98.68%)
15.94%
(for 164km)
18.8%
(for 164km)
1609
(95.55%)
1613
(95.78%)
30.46%
(for 197 km)
32.54%
(for 197 km)
DELHI-KOLKATA
[1453 KM]
1451
(99.86%)
1451
(99.86%)
96.07%
(for 366 km)
96.49%
(for 283 km)
TOTAL GQ
 [5846 KM]
5749
(98.34%)
5756 
(98.46%)
55.56%
(for 727 km)
57.11%
(for 664 km)
 