GOLDEN QUARDRILATERAL:Overall Progress Corridor Wise Including Completed Length as on 30th June 2010
All lengths in Kms.
CORRIDOR AND ITS TOTAL LENGTH
(in km)
Cumulative length completed in km (in %)
Cum % progress of contracts under implementation
By end of last month
By end of month under report
By end of last month
By end of month under report
DELHI-MUMBAI
[1419 KM]
1419
(100%)
1419
(100%)
-
-
MUMBAI-CHENNAI
[1290 KM]
1288
(99.84%)
1288.45
(99.87%)
31.2%
(for 164km)
31.2%
(for 164km)
KOLKATA- CHENNAI
[1684 KM]
1632
(96.91%)
1633.37
(96.99%)
44.01%
(for 197 km)
44.9%
(for 197 km)
DELHI-KOLKATA
[1453 KM]
1452
(99.93%)
1452.30
(99.95%)
97.07%
(for 283 km)
97.58%
(for 283 km)
TOTAL GQ
[5846 KM]
5791
(99.05%)
5793.12
(99.09%)
64.01%
(for 664 km)
64.51%
(for 664 km)