DETAILS OF MAINTENANCE
CONTRACTS VALUING Rs. 10 CRORES CONCLUDED
|
| WITH EFFECT FROM FEBRUARY-2006 |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| Sr. No. | Tender No. | Item/ Nature of work | Mode of Tender Enquiry- open tender / Limited Tender | Date of Publication of NIT | Type of bidding (single / Two bid system) | Last date of reciept of tender as per NIT/ extended if any | Nos. of tenders received | Nos. of the names of parties qualified after technical evaluation | Nos. of the names of parties not qualified after technical evaluation | Award of Tender | Contract no. & date | Name of contractor | Value of contract | Scheduled date of commncement of work | remarks |
| 1. | - | Periodic maintenance works comprising of bituminous concrete overlay on NH-2 (Delhi-Agra Section) (km 18.80 to km 199.60) in the State of Haryana/ U.P | Open Tender | 10.10.2006 | Single (Two Envelope System) | 07.11.2006 | Three | Three, (i) M/s. Shakeel Haider Engineers & Contractors (ii) M/s. C & C Constructions Ltd. (iii) M/s. PNC Construction Co. Ltd. | Nil | L-1 | NHAI/CM/O&M/NH-2/B-18 dated 02.02.07 | M/S Shakeel Haider, Engineers and Contractors | Rs. 398428354.00 | 17.02.2007 | - |
| 2. | - | Operation and maintenance contract for Nellore-Chilkaluripet section of NH-5 (Km.1366.547 – Km.1183.027) | Open tender | 31.07.2006 | Single (Two Envelope System) | 22.09.2006 | Four |
Four (i) M/s. Elsamex, S.A. - SSJV Projects Pvt. Ltd. (JV) (ii) M/s. IJM (India) Infrasructure Ltd. (iii) M/s. MBL Infrastructure Ltd. (iv) M/s. SMS Infrastructure Ltd. |
Nil | L-1 | NHAI/CM/O&M/NH-5/B-14 dated 01.03.2007 | M/s. SMS Infrastructure Ltd | Rs. 457999128.00 | 16.03.2007 | - |
| 3. | - | Periodic maintenance works comprising of bituminous concrete overlay on Gurgaon-Kotputli-Amer Section (km 42 to km 248) in the state of Haryana and Rajasthan on NH-8 | Open tender | 30.11.2006 | Single (Two Envelope System) | 29.12.2006 | Eight | Seven; (i) M/s. Chetak Enterprises Pvt. Ltd. (ii) M/s. Dinesh Chandra R Agarwal Infracon Pvt. Ltd. (iii) M/s. Ranjit Buildcon Ltd. (iv) M/s. Backbone Enterprises Ltd. (v) M/s. Sadbhav Engineering Ltd. (vi) M/s. PNC Construction Ltd. (vii) M/s. SMS Infrastructure Ltd. | One; M/s. Shakeel Haider Engineers & Contractors | L-1 | NHAI/CM/O&M/NH-8/B-19 dated 23.03.2007 | M/s. Backbone Enterprises Ltd | Rs. 689518080.00 | 07.04.2007 | - |
| 4. | - | NHAI/CM/C-22/2006/II Short Term Improvement & Rotine Maintenance of Samakhiyali-Gandhidham section from Km 306.000 to Km 362.160 of NH-8A in the State of Gujarat | Open tender | 6.1.2007 | Single (Two Envelope System) | 8.2.2007 | 4 |
2 a) M/s Patel Infrastructure Pvt Ltd b) M/s Dinesh Chandra Agrwal Infracon Pvt Ltd. |
2 a) M/s Elsamax SA b) M/s Kalthia Engineering & Const. |
Lowest Tenderer | NHAI/CM/C-22/2006/II dt. 25.5.07 | M/s Patel Infrastructure Pvt Ltd | Rs 131873844 | 16.6.07 | - |
| 5. | - | NHAI/CM/ Vaniyambadi-Ranipet/2006 Short term improvement and routine maintenance of Vaniymbadi to Waljapeth from Km.50.112 to Km.148.201 of NH-46 in the state of Tamil Nadu | Open tender | 13.2.2007 | Single (Two Envelope System) | 13.3.2007 | 3 |
3 a) M/s A Srinivasulu b) M/s SRK Const. c) M/s SMS Inf. |
Nil | Lowest Tenderer | NHAI/CM/Vaniyambadi-Ranipet/2006 dt. 11.7.2007 | M/s SMS Inf Ltd | Rs 14,19,15,979/- | 18.7.07 | - |
| 6. | - | Short term improvement and routine maintenance contract of National Highway No.1 from Panipat to Jalandhar (Km.96.000 to Km.387.100) | Open tender | 18.05.2007
|
Single (Two Envelope System) | 15.06.2007 | Two | Two; (i) M/s. Hitech Drillers Pvt. Ltd. (ii) M/s. Shakeel Haider Engineers & Contractors | Nil | L-1 | NHAI/CM/O&M/NH-1/B-22 dated 09.08.2007 | M/s Hitech Drillers Pvt. Ltd | Rs. 366671263.00 | 16.08.2007 | - |
| 7. | - | Short Term improvement and routine maintenance of Kishangarh to Jojro Ka Kheda (Km 0.00 to 35.00 of NH 79 - A & 15.00 to Km 163.900 of NH-79) in the State of Rajasthan. | Open tender | 25.01.2007
|
Single (Two Envelope System) | 23.02.2007 | 5 | 1. M/s Prakash Asphaltings & Toll Highways (I) Ltd. 2. M/s NG ProjectsLtd. 3. M/s Braham Prakash Modi 4. M/s SMS Infrastructure Ltd. 5. M/s Kalathia Engineering & Const. | Nil | Yes | 13.06.2007 | M/s Kalthia Engineering & Const. Ltd | 318933006.54 | 27.06.2007 | - |
| 8. | NHDP III/BOT/TN/001 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | 2 | 1 Ramanathan &
Co
2 C.K. Rajan |
Nil | On L1 basis . | NHAI/BOT- 1/11026/05/2005/294 | M/s. A Ramanathan & Co. | 1,60,38,112.20 | 21.02.2006 | - |
| 9. | NHDP III/BOT/TN/002 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | 2 | 1 I Vitrival
> 2 J. Senthil Kumar |
Nil | On L1 basis . | NHAI/BOT- 1/11026/13/2005/306 | I Vitrival | 1,74,41,820 | 14.03. 2006 | - |
| 10. | NHDP III/BOT/TN/003 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | three | 1 R. Krishnan
> 2 I Vitrival 3 J. Senthil Kumar |
Nil | On L1 basis . | NHAI/BOT- 1/11026/14/2005/305 | R. Krishnan | 1,27,69,375 | 14.03.2006 | - |
| 11. | NHDP III/BOT/TN/006 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | two | 1 V. Kannan
> 2 S.P.L Infrustucture > 3 J. Senthil |
Nil | On L1 basis . | NHAI/BOT- 1/11026/15/2005/308 | V.Kannan | 2,05,52,296 | 14.03.2006 | - |
| 12. | NHDP III/BOT/TN/007 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | two | 1 K. Ramakrishna
> 2.V.Kannan |
Nil | On L1 basis . | NHAI/BOT- 1/11026/06/2005/288 | K. Ramakrishna | 2,84,38,079.50 | 21.02.2006 | - |
| 13. | NHDP III/BOT/TN/008 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | four | 1 Sri durga
Construction
2 A Ramanathan 3 S.M. Sait > 4 V. Kannaiyan |
Nil | On L1 basis . | NHAI/BOT- 1/11026/16/2005/309 | Sri durga Construction | 3,36,00,590 | 14.03.06 | - |
| 14. | NHDP III/BOT/TN/009 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | one | R. Bala Krishnan | Nil | Single bid System. | NHAI/BOT- 1/11026/19/2005/307 | R. Bala Krishnan | 96,82,191 | 14.03.06 | - |
| 15. | NHDP III/BOT/TN/010 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | three | 1. L Purushotanan 2 Sri Mahalakshmi Engg. Const. 3 V.Kannan |
Nil | On L1 basis . | NHAI/BOT- 1/11026/07/2005/289 | L Purushotanan | 1,07,08,679,36 | 21.02.06 | - |
| 16. | NHDP III/BOT/TN/011 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | four | 1. Mahalakshmi Engg. 2 Sri Ramajeyam Const. 3 Moahan Reddy 4 T.S. R. Const. |
Nil | On L1 basis . | NHAI/BOT- 1/11026/08/2005/293 | Sri Ramajeyam | 1,19,10,620 | 21.02.06 | - |
| 17. | NHDP III/BOT/TN/012 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | three | 1.Mohan Reddy
> 2 Sri Ramajeyam Const. > 3 Deepam Const. |
Nil | On L1 basis . | NHAI/BOT- 1/11026/09/2005/292 | Deepam Const | 1,29,14,900 | 21.02.06 | - |
| 18. | NHDP III/BOT/TN/014 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | four | 1.Shasi Road
Finisher 2 Mohan Reddy 3 P. Baskar 4 J. Shentil Kumer |
Nil | On L1 basis . | NHAI/BOT- 1/11026/20/2005/261 | Mohan Reddy | 2,45,43,119.37 | 15.04.06 | - |
| 19. | NHDP III/BOT/TN/015 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | two | 1.A Ramanathan &
Co. 2 C.K Rajan. |
Nil | On L1 basis . | NHAI/BOT- 1/11026/11/2005/291 | C.K Rajan | 1,60,74,930 | 21.02.2006 | - |
| 20. | NHDP III/BOT/TN/016 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | three | 1. Guru Moorthy
Engg.Enterprise 2. V. Kannaiyan > 3. C.K. Rajan |
Nil | On L1 basis . | NHAI/BOT- 1/11026/19/2005/314 | Guru Moorthy Engg.Enterprise | 1,61,82,000 | 14.03.2006 | - |
| 21. | NHDP III/BOT/TN/017 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | two | 1.K. G. Laxmipathi
& Co.
2.Shanti Construction. |
Nil | On L1 basis . | NHAI/BOT- 1/11026/22/2005 | Shanti Construction | 1,36,00,000 | 27.03.06 | - |
| 22. | NHDP III/BOT/TN/018 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | two | 1.K. G. Laxmipathi
& Co.
2.Shanti Construction. |
Nil | On L1 basis . | NHAI/BOT- 1/11026/23/2005 | K. G. Laxmipathi & Co | 1,84,86,454 | 27.03.06 | - |
| 23. | NHDP III/BOT/TN/023 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 and the date was extend up to 20.02.2006 | two | 1.M/s. Gurumoorthy
Engg. Enterprise
2.Janardan |
Nil | On L1 basis . | NHAI/BOT- 1/11026/28/2005/315 | Janardan | 92,35,735 | 14.03.06 | - |
| 24. | NHDP III/BOT/TN/024 | Filling of pot holes , patching & renewals etc. | Open tender | Jan-06
|
Two bid system | 6.02.2006 | two | 1.Masilamani
2.Subramanian |
Nil | On L1 basis . | NHAI/BOT- 1/11026/12/2005/290 | Masilamani | 1,85,32,327.64 | 21.02.06 | - |
| 24. | NHAI/CM/D-13 A/2006 Short Term Improvement & Routine Maintenance of Bhubneshwar-Cuttack-Jagatpur-Chandikhole section of NH-5 ( Km 0.000 to Km 61.00 and Km 414.00 to Km 419.200) | Road Maintenance, Road Property Management, Engineering Improvement, Incident Management & General Items | Open Tender | 6.6.05 | Two Bid System | 15.7.05 | five | 5 (i) M/s Sadbhav Engineering Ltd (ii) M/s Harish Chandra Ltd, (iii) M/s Rohit Das Const. Pvt Ltd, (iv) M/s Maheshwari Bros Pvt Ltd, (v) M/s Durga Condev Pvt Ltd | Nil | Lowest Tenderer | NHAI/CM/D-13/2006 dt. 20.4.2006 | M/s Sri Duga Condve Pvt Ltd | Rs 25,21,66,356/- | 6.5.06 | - |
| 25. | NHAI/CM/Agra-Gwalior/2005 Short Term Improvement & Routine Maintenance of Agra-Gwalior section from Km 8.00 to Km 103.00(excluding Km 51.00 to Km 61.00) of NH-3 | Road Maintenance, Road Property Management, Engineering Improvement, Incident Management & General Items | Open Tender | 18.07.05 | Two Bid System | 18.8.2005 | Six | 4 a) M/s PNC Constn Co. Ltd. b) M/s TR Trehan Constn. Pvt. Ltd c) M/s Himalayan Constn. Co. d) Mcnally Bharat engineering Co Ltd | 2 a) M/s Apco Costn. Pvt. Ltd. b) M/sSinghal Builders | Lowest Tenderer | NHAI/CM/Agra-Gwalior/2006 dt. 16.05.06 | M/s Himalayan Constn. Co. | Rs 133610075 | 30.05.06 | - |
| 26. | NHAI/CM/Krishnagiri-Vaniyambadi Short Term Improvement & Routine Maintenance of Athipali-Krishnangiri section from Km 33.015 to Km 94 of NH-7 and Krishnagiri - Vaniyambadi section from Km 0 to Km 50.112 of NH-46 in Tamil Nadu | Road Maintenance, Road Property Management, Engineering Improvement, Incident Management & General Items | Open Tender | 9.2.2006 | Two Bid System | 9.3.2006 | Two | 1 a) M/s A Srinivasulu & Co. | 1 M/s GVR Const. Pvt. Ltd. | Single Tender | - | - | |||
| 27. | Short term improvement and routine maintenance contract of National Highway No.1 from Panipat to Jalandhar (Km.96.000 to Km.387.100) | Road Maintenance, Road Property Management, Engineering Improvement, Incident Management & General Items | Open Tender | 26.11.2005 | Two Bid System | 26.12.2005 | Three | 3, (i) M/s.Hightech Drillers Pvt. Ltd. (ii) M/s Maheshwari Brothers Ltd. (iii) M/s. PNC Construction Co. Ltd. | Nil | Lowest Bidder | NHAI/CM/O&M/NH-1/B-15 dated 23.05.2006 | M/s.Hightech Drillers Pvt. Ltd | Rs.42,62,75,070.00 | 15.06.2006 | - |
| 28. | Short term improvement and routine maintenance contract of National Highway No.2 from Barwa Adda to Panagarh (Km.398.750 to Km.515.236) | Road Maintenance, Road Property Management, Engineering Improvement, Incident Management & General Items | Open Tender | 26.11.2005 | Two Bid System | 26.12.2005 | Four | 4, (i) M/s. Rajpath Contractors and Engineers Ltd. (ii) M/s. Banowarilal Agarwal & Pvt. Ltd. (iii) M/s. Maheshwari Brothers Ltd. (iv) M/s. Calcutta Industrial Supply Corporation | Nil | Lowest Bidder | NHAI/CM/O&M/NH-2/B-16 dated 24.08.2006 | M/s. Maheshwari Brothers Ltd | Rs.21,02,01,859.47 | 01.09.2006 | - |
| 29. | Short term improvement and routine Maintenance contract of National Highway No.5 from Chilkaluripet to Vijayawada (Km.355.000 to Km.434.150) and from Vijaywada to Eluru (km.3.400 to Km.81.600) | Road Maintenance, Road Property Management, Engineering Improvement, Incident Management & General Items | Open Tender | 26.11.2005 | Two Bid System | 26.12.2005 | 3 | 3, (i) M/s. Nagarjuna Construction Co. Ltd. (ii) M/s. Maheswari Brothers Ltd. (iii) M/s. Gammon India Ltd | Nil | Lowest Bidder | NHAI/CM/O&M/NH-5/B-17 dated 24.08.2006 | M/s. Maheshwari Brothers Ltd. | Rs.31,44,10,141.65 | 16.09.2006 | - |