Chainage Chart of NHDP Phase III |
| Status : 31st March 2013 |
S.NO |
NH | Length (Km) |
Present Status |
Contractor & Nationality |
NHDP Phase III |
||||
1 |
220 | 134 | Under Implementation | Transstroy-OJSC Consortium Ltd Indian-Russian |
2 |
57A | 9.258 | Under Implementation | GPT-RDS Consortium Ltd Indian |
3 |
80 | 69.27 | Under Implementation | BSCPL -C & C Consortium Indian |
4 |
77 | 86 | Under Implementation | BSCPL-C&C(JV) Indian |
5 |
31 | 140 | Under Implementation | Punj Lloyd Infrastructure Ltd. Indian |
6 |
28A | 68.79 | Under Implementation | Tantia-Jiangsu (JV) Indian-China (JV) |
7 |
59 | 117.6 | Under Implementation | ESSEL Infra & CR-18 Consortium Indian-china |
8 |
33 | 41.314 | Under Implementation | Abhijeet Infrastructure Ltd-Corporate Ispat Alloy Ltd(JV) Indian |
9 |
19 | 65 | Under Implementation | Madhucon Projects Ltd Indian |
10 |
59 | 87.285 | Under Implementation | BSPCL Ltd Indian |
11 |
42 | 112 | Under Implementation | Ashoka Buildcon Indian |
12 |
71 | 48.6 | Under Implementation | Vijai Infrastructure Ltd. Indian |
13 |
65 | 78 | Balance for award | |
14 |
1 | 35.93 | Completed | Rohan Builders Pvt. Ltd. - Rajdeep Buildcon Pvt. Ltd. - IDFC Ltd. Consortium Indian |
15 |
54 | 140 | Balance for award | |
16 |
44 | 116 | Balance for award | |
17 |
52 | 314 | Balance for award | |
18 |
52A | 9 | Balance for award | |
19 |
4 | 19.5 | Under Implementation | Navyuga Engineering Co. Ltd. Indian |
20 |
35 | 60 | Balance for award | |
21 |
14 | 244.12 | Under Implementation | L&T Infrastructure Development Projects Ltd. Indian |
22 |
12 | 297 | Balance for award | |
23 |
86Ex | 53.78 | Under Implementation | Pratibha Industries-Abhyuday Housing Construction Ltd Indian |
24 |
13 | 97.22 | Completed | SEL-MCL Consortium Indian |
25 |
21 | 30 | Balance for award | |
26 |
200 | 39 | Balance for award | |
27 |
6 | 80 | Completed | Ashoka - IDFC Consortium Indian |
28 |
10 | 20 | Balance for award | |
29 |
10 | 63.49 | Under Implementation | KCT - ERA consortium Indian |
30 |
58 | 46 | Balance for award | |
31 |
12 | 83 | Under Implementation | GVK Development Projects Pvt Ltd Indian |
32 |
48 | 77.23 | Under Implementation | Larsen & Toubro Ltd. Indian |
33 |
36 | 124 | Balance for award | |
34 |
200 | 98 | Balance for award | |
35 |
7 | 9.98 | Completed | SOMA - NCC - MAYTAS Consortium Indian |
36 |
6 | 82.685 | Completed | Ashoka - IDFC Consortium Indian |
37 |
91 | 126 | Under Implementation | SREI - PNC - GALFAR Consortium Indian - Dubai |
38 |
72 | 39 | Under Implementation | ERA - SIBMOST(JV) Indian - Russian |
39 |
33 | 75 | Under Implementation | ITNL-Punj Lloyd Ltd.(JV)
(Hazaribagh Ranchi Express way ltd) Indian |
40 |
13 | 120.03 | Under Implementation | Ramkey Infrasructure Ltd Indian |
41 |
13 | 97.89 | Under Implementation | GMR-OSE Consortium Indian |
42 |
202 | 35.65 | Completed | Sadbhav Engineering Ltd. (Hyderabad-Yadgiri Tollways Pvt. Ltd.) Indian |
43 |
59 | 155.15 | Under Implementation | IVRCL Infrastructure Projects Ltd. Indian |
44 |
52A | 22 | Balance for award | |
45 |
11 | 54 | Under Implementation | RIL-AAA- JTEG Consortium Indian-China |
46 |
12 | 150 | Under Implementation | IRB-MRM Consortium Indian |
47 |
75 | 100 | Balance for award | |
48 |
4 | 20 | Balance for award | |
49 |
8A | 71.4 | Under Implementation | Reliance Infra Projects Ltd. Indian |
50 |
210 | 100 | Balance for award | |
51 |
47 | 56 | Balance for award | |
52 |
8 | 93.56 | Under Implementation | Isolux-Soma Consortium Spain-Indian |
53 |
17 | 126.6 | Under Implementation | Transstry-OJSC Consortium Indian-Russian |
54 |
39 | 28 | Balance for award | |
55 |
17 | 90 | Under Implementation | Navayuga - KPCL Consortium Indian |
56 |
21 | 42.9 | Completed | BSCPL - C & C Consortium Indian |
57 |
43 | 23 | Balance for award | |
58 |
49 | 186 | Balance for award | |
59 |
9 | 145 | Under Implementation | L&T Infrasructure Developement Projects Ltd Indian |
60 |
24 | 121 | Under Implementation | IL & FS Transportation Ltd. Indian |
61 |
58, 72 | 80 | Under Implementation | ERA-SIBMOST Indian - Russian |
62 |
39 | 111 | Balance for award | |
63 |
67 | 74 | Balance for award | |
64 |
6 | 45.43 | Under Implementation | JMC Projects India Ltd. Indian |
65 |
48 | 81 | Completed | Lanco Devihalli Highways Pvt. Ltd. Indian |
66 |
69 | 13 | Balance for award | |
67 |
71A | 80.858 | Under Implementation | Sadbhav Engineering Ltd Indian |
68 |
17 | 84 | Under Implementation | Supreme Infrastructure India Ltd.-Mahavir Road & Infrastructure Pvt. Ltd.-China State Construction Engg. Hongkong Ltd. Indian-China |
69 |
22 | 103 | Balance for award | |
70 |
19 & 77 | 63 | Under Implementation | Gammon Infrastructure Ltd Indian |
71 |
83 | 125 | Balance for award | |
72 |
3 | 60 | Under Implementation | Larsen & Toubro Ltd. - ABL Consortium Indian |
73 |
66 | 38.61 | Completed | Maytas - NCC Consortium Indian |
74 |
66 | 4 | Balance for award | |
75 |
9 | 110.05 | Under Implementation | Navinya Buildcon-Atlantia Spa(JV) Indian-Italy |
76 |
9 | 105 | Under Implementation | IL & FS Transportation Network Ltd Indian |
77 |
200 | 28 | Balance for award | |
78 |
71 | 82.553 | Under Implementation | JMC-SREI(JV) Indian |
79 |
44 | 27 | Balance for award | |
80 |
54 | 50 | Balance for award | |
81 |
13 | 30 | Balance for award | |
82 |
6 | 67.8 | Under Implementation | IRB-MRM Consortium Indian |
83 |
45 | 88.273 | Completed | Reliance Energy Limited Indian |
84 |
67 | 79.7 | Under Implementation | Reliance Energy Limited Indian |
85 |
47 | 29 | Balance for award | |
86 |
1 & 24 | 8 | Balance for award | |
87 |
22 | 28.69 | Completed | Jaiprakash Associates-(Himalyan Expressways Pvt. Ltd.) Indian |
88 |
215 | 96 | Under Implementation | MBL-SREI Indian |
89 |
13 | 110.542 | Under Implementation | Sadbhav Engineering Limited Indian |
90 |
4 | 22.18 | Under Implementation | J.S.R. Construction Pvt Ltd Indian |
91 |
8D | 123.45 | Under Implementation | IDFC-PLUS Expessway Berhad Consortium Indian-Malaysian (JV) |
92 |
9 | 64.611 | Under Implementation | Madhucon Projects Ltd. Indian |
93 |
215 | 163 | Under Implementation | Gayatri Projects Ltd. Indian |
94 |
203 | 67 | Under Implementation | KSS-Valecha (Bhubneshwar Expressway Pvt. Ltd.) Indian |
95 |
6 | 88 | Under Implementation | Ashoka Buildcon Ltd-(Ashoka Sambalpur Baragarh Expressway Pvt. Ltd.) Indian |
96 |
85 | 92 | Under Implementation | Abhijeet Infrastructure Ltd. Indian |
97 |
210 & 67 | 110.372 | Under Implementation | Transstroy Ltd-OJSC Consortium Indian-Russian |
98 |
45B | 128.16 | Completed | Madhucon Projects Ltd. - SREI - Madhucon granites Ltd (JV) Indian |
99 |
17 | 83.2 | Under Implementation | KMC Construction Ltd. Indian |
100 |
18 | 188.752 | Under Implementation | KMC Construction Ltd. - IVRCL Consortium Indian |
101 |
7 | 14.38 | Completed | GVR Construction Pvt. Ltd. Chennai Indian |
102 |
34 | 103 | Under Implementation | Hindustan Construction Company Ltd. Indian |
103 |
17 | 81.5 | Under Implementation | KMC Construction Ltd. Indian |
104 |
4 | 79.724 | Completed | Lanco Hoskote Highway Pvt. Ltd. Indian |
105 |
9 | 100.06 | Under Implementation | Coastal-SREI Consortium Indian |
106 |
24 | 151.2 | Under Implementation | ERA-SIBMOST Indian-Russian |
107 |
205 | 124.7 | Under Implementation | Transstroy -OJSC Consortium(JV) Indian-Russian |
108 |
34 | 103 | Under Implementation | Hindustan Construction Company Ltd. Indian |
109 |
34 | 50 | Under Implementation | Hindustan Construction Company Ltd. Indian |
110 |
9 | 181.63 | Completed | GMR-Punj LLOYD Consortium(GMR-Hyderabad Vijayawada Expressway Pvt. Ltd.) Indian |
111 |
15 | 106 | Under Implementation | IRB-MRM Pvt Ltd. Indian |
112 |
73 | 107 | Under Implementation | Gammon Infrastructure Projects Ltd. Indian |
113 |
67 | 56 | Under Implementation | Madhucon Projects Ltd. Indian |
114 |
6 | 132.9 | Under Implementation | Isolux-Soma Consortium (JV) Spain-Indian |
115 |
31 | 112.982 | Under Implementation | Navayuga Engineering Company Ltd. Indian |
116 |
68 | 136.357 | Under Implementation | Reliance Energy Limited Indian |
117 |
34 | 78 | Under Implementation | SEW Infra. Indian |
118 |
30 | 50.6 | Under Implementation | BSC-C & C (JV) Indian |
119 |
69 | 125 | Under Implementation | Transstroy (India) Ltd. Indian |
120 |
71 | 68 | Under Implementation | Unity Infraprojects Ltd. Indian |
121 |
34 | 84 | Under Implementation | Madhucon Projects Ltd. Indian |
122 |
66 | 176.51 | Under Implementation | Transstroy (I) Ltd. - Corporation Transstroy OJSC Consortium Indian - Russian |
123 |
44 | 102 | Under Implementation | Simplex Infrastructure Ltd. Indian |
124 |
21 | 84.32 | Under Implementation | IL & FS Transportation Networks Ltd. Indian |
125 |
95 | 78 | Under Implementation | Essel Infra Projects Ltd.- Pan Indian Networks Ltd. Indian |
126 |
30 & 84 | 124.85 | Under Implementation | Gammon Infrastructure Projects Ltd Indian |
127 |
10 | 98.81 | Under Implementation | Sadbhav Engg. Limited Indian |
128 |
87 | 93.226 | Under Implementation | ERA Infra Engineering Ltd.-OJSC-SIBMOST (JV) Indian - Russian |
129 |
33 | 163.5 | Under Implementation | Madhucon Projects Ltd. Indian |
130 |
11 | 43.887 | Under Implementation | G.R.Infraprojects Ltd. Indian |
131 |
67 | 53.93 | Under Implementation | Transstroy-OJSC Consortium Indian |
132 |
12 | 88.09 | Under Implementation | Keti Constructions Ltd. Indian |
133 |
3 | 88.79 | Completed | Hindustan Construction Company Ltd. -Laing-Sadbhav Consortium Indian-UK |
134 |
4A | 81.89 | Under Implementation | GVR Infra Projects-RMN Infrastructure Ltd Indian |
135 |
17 | 139 | Under Implementation | IVRCL Infrastructure & Projects Ltd Indian |
136 |
4A | 69 | Under Implementation | IRB-MRM Consortium Indian |
137 |
47 | 83.6 | Under Implementation | ISOLUX-SOMA Spain-Indian |
138 |
50 | 30 | Completed | IRB - Madhujaya Consortium Indian |
139 |
3 | 14 | Completed | Guna Infrastructure Ltd. Indian |
140 |
58 | 79 | Completed | Nagarjuna Construction Co. Ltd. - MAYTAS Consortium Indian |
141 |
3 | 118 | Completed | IRCON-SOMA Consortium Indian |
142 |
11 | 108 | Completed | JMTPL(I) Corporation Project Malaysian |
143 |
11 | 57 | Completed | Madhucon Projects Ltd. - SREI Indian |
144 |
3 | 100 | Completed | Gammon India Ltd. - Sadbhav - Billimoria Consortium Indian |
145 |
6 | 43.485 | Under Implementation | Apollo(UK) - JLI(UK) - DSC(Indian) - LOR(UK) Consortium UK - Indian JV |
146 |
1 | 49 | Completed | IVRCL Infrastructure Projects Ltd. Indian |
147 |
21, 22 | 36 | Completed | GMR Energy Ltd. & GMR Infrastruture Ltd. Consortium Indian |
148 |
6 | 50 | Completed | Oriental Structural Engineers Pvt. Ltd.- Delhi Brass Consortium Indian |
149 |
3 | 82.8 | Completed | Navyuga Engineering Co. Ltd. Indian |
150 |
3 | 80 | Completed | Oriental Structural Engineers Pvt. Ltd.- Delhi Brass Consortium Indian |
151 |
11 | 45 | Completed | Oriental Structural Engineers Pvt. Ltd.- Delhi Brass Consortium Indian |
152 |
24 | 75 | Completed | Apollo(UK) - JLI(UK) - DSC(Indian) - LOR(UK) Consortium UK - Indian JV |
153 |
6 | 40 | Under Implementation | Atlanta - SREI Consortium (JV) Indian |
|
|