Chainage Chart of Corridor East - West
Status : 31st January 2014

S.NO
Stretch
State
Funded By

NH Length
(Km)
Total Project Cost

Present Status

Contractor & Nationality
East - West Corridor

1
Silchar-Udarband (AS-1)
Km 309 to Km 275.00
Assam
NHAI

54 32 154.57  Under Implementation Punj Lloyd Ltd.
Indian

2
Udarband to Harangajo (AS-14)
Km 275.00 to Km 244.00
Assam

54 31   Balance for award

3
Harangajo to Maibang (AS-21)
Km 165.4.00 to Km 190.587
Assam
NHAI

54 26 386.1  Under Implementation N.K.C - JKM (JV)
Indian

4
Harangajo to Maibang (AS-22)
Km 140.70 to Km 164.08
Assam
NHAI

54 24 363.74  Under Implementation N.K.C - JKM (JV)
Indian

5
Harangajo to Maibang (AS-23)
Km 126.450 to Km 140.700 , km 164.080 to km. 165.400
Assam
NHAI

54 16 280  Under Implementation Hindustan Construction Company Ltd.
Indian

6
Maibang to Lumding (AS-27)
Km 40.000 to Km 60.500
Assam
NHAI

54 21 200  Under Implementation Gayatri -ECI (JV)
Indian

7
Maibang to Lumding (AS-26)
Km 60.500 to Km 83.400
Assam
NHAI

54 23 167.64  Under Implementation Simplex Infrastructure Ltd.
Indian

8
Maibang to Lumding (AS-25)
Km 83.400 to Km 111.000
Assam
NHAI

54 28 385.13  Under Implementation Maytas Infra Ltd.
Indian

9
Maibang to Lumding (AS-24)
Km 111.000 to Km 126.450
Assam
NHAI

54 15 280.13  Under Implementation N.K.C Projects Pvt. Ltd.
Indian

10
Lumding to Daboka (AS-15)
Km 40.00 to Km 22.00
Assam
NHAI

54 18 130  Completed Patel - KNR (JV)
Indian

11
Lanka to Daboka (AS-16)
Km 22.00 to Km 2.4
Assam
NHAI

54 24.03 225  Completed Punj Lloyd Ltd.
Indian

12
Daboka to Nagaon (AS-17)
Km 36 to Km 5.5
Assam
NHAI

36 30.5 225  Completed Maytas Infrastructure Ltd.
Indian

13
Nagaon bypass (AS-18)
Km 5.5(NH-36) to km 262.7(NH-37) and from km 262.70 to km 255
Assam
NHAI

37 23.66 230  Completed Patel - KNR (JV)
Indian

14
Nagaon to Dharmatul (AS-2)
km 255 to km 230
Assam
NHAI

37 25 264.72  Under Implementation Madhucon Projects Ltd.
Indian

15
Dharamtul to Sonapur (AS-19)
Km 230.5 to Km 205
Assam
NHAI

37 25 200  Under Implementation Maytas Infrastructure Ltd.
Indian

16
Dharamtul to Sonapur (AS-20)
Km 205.00 to Km 183
Assam
NHAI

37 22 160  Under Implementation KMC Construction Ltd.
Indian

17
Sonapur to Guwahati (AS-3)
km 183 to km 163.895
Assam
NHAI

37 19 245  Under Implementation Maheshwari Brothers Ltd.-Telecommunication Consultant India Ltd.
Indian

18
Guahati bypass (EW/7)
km 163.895 - km 156
Assam
NHAI

37 8 54.87  Completed Valecha Engineering Ltd.
Indian

19
Guwahati Bypass (EW-14/AS)
Km. 156.00 to Km. 146.00
Assam
NHAI

37 10.5 63.69  Completed Banvari Lal Agarwal (BLA) - CISC - C&C Construction (JV)
Indian

20
Brahmputra Bridge (AS-28)
Km.1126.00 to Km.1121.00
Assam
NHAI

31 5 217.61  Under Implementation Gammon India Ltd.
Indian

21
Guwahati to Nalbari (AS-4)
Km.1121.00 to Km.1093.00
Assam
NHAI

31 28 175.96  Under Implementation Punj Lloyd Ltd.
Indian

22
Guwahati to Nalbari (AS-5)
Km.1093.00 to Km.1065.00
Assam
NHAI

31 28 198.16  Under Implementation Punj Lloyd Ltd.
Indian

23
Nalbari to Bijni (AS-6)
Km.1065.00 to Km.1040.3
Assam
NHAI

31 25 225  Under Implementation Dinesh Chandra R. Agarwal - Infracon Pvt. Ltd. - Banowari Lal Agarwalla Pvt. Ltd. - Brahmaputra Constorium Ltd.
Indian

24
Nalbari to Bijni (AS-7)
Km.1040.3 to Km.1013.00
Assam
NHAI

31 27.3 208  Under Implementation KMC Construction Ltd.
Indian

25
Nalbari to Bijni (AS-8)
Km.1013.00 to Km.983.00
Assam
NHAI

31 30 200  Under Implementation Punj Lloyd Ltd.
Indian

26
Nalbari to Bijni (AS-9)
Km.983.00 to Km.961.5
Assam
NHAI

31 21.5 142  Under Implementation Punj Lloyd Ltd.
Indian

27
Bijni to Assam/WB Border (AS-10)
Km.93.00 to Km. 60.00
Assam
NHAI

31C 33 237.8  Under Implementation GPL-ECI (JV)
Indian

28
Bijni to Assam/WB Border (AS-11)
Km.60.00 to Km.30.00
Assam
NHAI

31C 30 195  Under Implementation GPL-ECI (JV)
Indian

29
Bijni to Assam/WB Border (AS-12)
Km.30.00 to Km. 0.00
Assam
NHAI

31C 30 230  Under Implementation Progressive Construction Ltd.
Indian

30
Assam/WB Border to Gairkatta (WB-1)
Km.255.00 to Km.223.00
West Bengal
NHAI

31C 26.5 221.82  Completed Italian Thai Dev. Projects Co. Ltd.
Thailand

31
Ghoshukur (km 351 of NH 31) to Salsalabari (km 226 of NH 31C) via Fulbari- Mainagnri - Dhumpgiri - Falkata (3 Packages)

West Bengal

31, 31C 201   Balance for award

32
Silliguri to Islampur (WB-6)
Km.551.00 to Km.526.00
West Bengal
NHAI

31 25 155  Completed B. Seenaiah & Co. (Projects) Ltd.
Indian

33
Siliguri to Islampur (WB-7)
Km.526.00 to Km.500
West Bengal
NHAI

31 26 225  Under Implementation IRCON International Ltd.
Indian

34
Dalkola Islampur Sub section 2(EW/6)
km 500 to km 476.15
West Bengal
NHAI

31 23.85 90.06  Completed Lanco Construction Ltd
Indian

35
Dalkola - Islampur (EW/5)
km 470 - km 447
West Bengal
NHAI

31 23 72.56  Completed Progressive Construction Ltd.
Indian

36
Purnea - Gayakota (EW/4)
km 476.15 - km 470 & km 419 - km 410
Bihar
NHAI

31 15.15 62.98  Completed Progressive Construction Ltd.
Indian

37
Purnea - Gayakota (EW-12/BR)
km 447 - km 419
Bihar
NHAI

31 28 205.73  Completed Lanco Construction Ltd - Rani (JV)
Indian

38
Purnea-Forbesganj (BR-1)
km 309.0 to km.268
Bihar
NHAI

57 42.5 276  Completed Progressive Construction Ltd.
Indian

39
Purnea-Forbesganj (BR-2)
km 268.0 to km.230
Bihar
NHAI

57 36.7 310  Completed Progressive Construction Ltd.
Indian

40
Forbesganj-Simrahi (BR-3)
km 230 to km 190
Bihar
NHAI

57 34.87 332.94  Under Implementation Gammon India Ltd.
Indian

41
Simrahi to Ring bund (missing link) (BR-4)
km 190 to km 165
Bihar
NHAI

57 15.15 100.5  Completed Simplex Infrastructure Ltd.
Indian

42
Kosi Bridge including approaches and Guide Bond & Afflux Bond (BR-5)
km 155 to km 165
Bihar
Annuity

57 10.63 418.04  Completed Gammon india Ltd. - GIPL Consortium
Indian

43
Ring bunds to Jhanjharpur (BR-6)
km 155 to km 110
Bihar
NHAI

57 38.55 340  Completed BSCPL - C&C (JV)
Indian

44
Jhanjhapur to Darbanga (BR-7)
km 110 to km 70
Bihar
NHAI

57 37.59 340  Completed Madhucon Projects Ltd.
Indian

45
Darbanga to Muzzaffarpur (BR-8)
km 70 to km 30
Bihar
NHAI

57 32.05 305  Completed B. Seenaiah & Co. (Projects) Ltd. - C & C (JV)
Indian

46
Darbanga to Muzzaffarpur (BR-9)
km 30 to km 0
Bihar
NHAI

57 37.75 291.8  Completed B. Seenaiah & Co. (Projects) Ltd. - C & C (JV)
Indian

47
Muzzaffarpur to Mehsi (LMNHP-12)
km 520 to km 480
Bihar
WB

28 40 275  Completed Progressive Construction Ltd. - MVR (JV)
Indian

48
Mehsi to Kotwa (LMNHP-11)
km 480 to km 440
Bihar
WB

28 40 239  Completed Madhucon Projects Ltd.
Indian

49
Kotwa to Dewapur (LMNHP-10)
km 440 to km 402
Bihar
WB/NHAI

28 38 240  Under Implementation Progressive Construction Ltd. - MVR (JV)
Indian

50
Deewapur to UP/Bihar Border (LMNHP-9)
km 402 to km 360.915
Bihar
WB/NHAI

28 41.085 300  Contract Terminiated

51
UP/Bihar Border to Kasia (LMNHP-8)
km 360.915 to km 319.8
Uttar Pradesh
WB

28 41.16 227  Completed Simplex
Indian

52
Kasia to Gorakhpur (LMNHP-7)
km 319.8 to km 279.8
Uttar Pradesh
WB

28 40 242  Completed NCC - VEE (JV)
Indian

53
Gorakhpur Bypass
Km. 251.7 to Km. 279.8
Uttar Pradesh
Annuity

28 32.6 600.24  Completed Gammon india Ltd. - GIPL - ATSL Consortium
Indian

54
Gorakhpur-Ayodhya (LMNHP-6)
Km. 251.70 to Km. 208.00
Uttar Pradesh
WB

28 44.86 239  Completed B. Seenaiah & Co. (Projects) Ltd.
Indian

55
Gorakhpur-Ayodhya (LMNHP-5)
Km. 208.00 to Km. 164.00
Uttar Pradesh
WB

28 44 227  Completed Nagarjuna Construction Co. Ltd.
Indian

56
Gorakhpur-Ayodhya (LMNHP-4)
Km. 164.00 to Km. 135.00
Uttar Pradesh
WB

28 29 205  Completed Hindustan Construction Company Ltd.
Indian

57
Ayodhya-Lucknow (LMNHP-3)
Km. 135.00 to Km. 93.075
Uttar Pradesh
WB

28 46 212  Completed Hindustan Construction Company Ltd.
Indian

58
Ayodhya-Lucknow (LMNHP-2)
Km. 93.075 to Km. 45
Uttar Pradesh
WB

28 47 217  Completed Hindustan Construction Company Ltd.
Indian

59
Ayodhya-Lucknow (LMNHP-1)
Km. 45.00 to Km.8.250
Uttar Pradesh
WB

28 36.75 193  Completed Hindustan Construction Company Ltd.
Indian

60
Lucknow Bypass (EW-15/UP)
Connecting NH-25 and NH-28 via NH56
Uttar Pradesh
NHAI

56A & B 22.85 111.78  Completed NKG Infrastructure Ltd.
Indian

61
Lucknow Kanpur Section (EW/2)
km 11.38 - km 21.8
Uttar Pradesh
NHAI

25 10.42 32.85  Completed Villayati Ram Mittal
Indian

62
Lucknow-Kanpur section (EW-8/UP)
Km.21.80 to Km. 44.00
Uttar Pradesh
NHAI

25 22.2 94.91  Completed Villayati Ram Mittal
Indian

63
Lucknow-Kanpur section (EW-9/UP)
km 44 - km 59.5
Uttar Pradesh
NHAI

25 15.5 50.02  Completed B.R. Arora & Associate (BRA) - TRGupta - BHARAT (JV)
Indian

64
Lucknow - Kanpur (EW/3B)
km 59.5 - km 75.5
Uttar Pradesh
NHAI

25 16 54  Under Implementation Neeraj Cement Structural Ltd
Indian

65
Ganga Bridge to Rama Devi Crossing (UP-6)
km 75.0 - km 80.06
Uttar Pradesh
NHAI

25 5.6 201.66  Under Implementation Gammon India Ltd.
Indian

66
Kanpur - Bhognipur section
km 492- km 449
Uttar Pradesh
WB

2 43   Completed

67
Bara to Orai
km 449 to 422 on NH-2 & km 255 to km 220
Uttar Pradesh
Annuity

2, 25 62.8 465  Completed NCC - KMC Consortium
Indian

68
Orai to Jhansi (UP-5)
km 220.0 - km 170.0
Uttar Pradesh
ADB

25 50 340.68  Completed IRCON International Ltd.
Indian

69
Orai to Jhansi (UP-4)
km 170.0 - km 104.0
Uttar Pradesh
ADB

25 68.2 451.97  Under Implementation Sunway Construction Ltd.
Malaysian

70
Jhansi Bypass (UP-3)
km 104.0 - km 91.0
Uttar Pradesh
ADB

25 15 158.06  Completed Oriental Structural Engineers Pvt. Ltd.
Indian

71
Jhansi-Shivpuri (UP/MP-1) (UP-11 km & MP - 30 km)
km 91 to km 50 (UP-11 km & MP-30 km)
Uttar Pradesh[11]/Madhya Pradesh[30]
ADB

25 41 220.31  Completed Oriental Structural Engineers Pvt. Ltd.
Indian

72
Jhansi-Shivpuri (EW-II - MP-2)
km 50 to km 15
Madhya Pradesh
ADB

25 35 213.69  Completed ITD- CemIndia (JV)
Thailand - Indian JV

73
Shivpuri Bypass & upto MP/RJ Border(EW-II - MP-I)
km 15 to km 0 of NH 25 & km 610 to km 579 of NH 76
Madhya Pradesh
ADB

25, 76 53 360.34  Completed CSCHK-Soma (JV)
China - Indian JV

74
RJ/MP Border to Kota (RJ-11)
km.579 to km.509
Rajasthan
ADB

76 70 349.59  Completed Larsen & Toubro Ltd. ECC DIVISION
Indian

75
RJ/MP Border to Kota (RJ-10)
km.509 to km. 449.15
Rajasthan
ADB

76 59.85 430.21  Completed KMC Construction Ltd.
Indian

76
RJ/MP Border to Kota (RJ-9)
km.449.15 to km. 406
Rajasthan
ADB

76 43.15 359.43  Completed Sunway Construction Ltd.
Malaysian

77
Kota Bypass (RJ-4)
km.406 to km. 381
Rajasthan
NHAI

76 26.42 250.39  Under Implementation ITD- CemIndia (JV)
Thailand - Indian JV

78
Chambal Bridge (RJ-5)

Rajasthan
NHAI

76 1.4 281.31  Under Implementation Hyundai eng. Cons. Co. Ltd. - M/s Gammon India Ltd.
Korean - Indian JV

79
Kota to Chittorgarh (RJ-8)
km.381 to km. 316
Rajasthan
ADB

76 65 528.44  Completed Punj Lloyd Ltd.
Indian

80
Kota to Chittorgarh (RJ-7)
km.316 to km. 253
Rajasthan
ADB

76 63 503.66  Completed CEC - Hindustan Construction Company Ltd. (JV)
China - Indian JV

81
Chittorgarh Bypass (RJ-6)
km.253 to km. 213
Rajasthan
ADB

76 40 447.9  Completed China Gezhouba Water & Power(Group) Co. Ltd.
China

82
Chittorgarh - Udaipur
km 220 - km 113.825
Rajasthan
NHAI

76 106   Completed

83
Gogunda to Udaipur (RJ-3)
km.104 km to km 73
Rajasthan
NHAI

76 31 288.06  Completed Ranjit - Tarmat (JV)
Indian

84
Bakaria to Gogunda (RJ-2)
km.73 km km 29
Rajasthan
NHAI

76 44 530.9  Completed SOMA - BSCPL(JV)
Indian

85
Swaroopganj to Bakaria (RJ-1)
km 29 km 0 (NH 76) & km 264 to km 249.7 (NH 14)
Rajasthan
NHAI

76, 14 43 243.11  Completed Agrawal JV
Indian

86
Palanpur to Swaroopganj (Rajasthan -42 km & Gujarat-34 km )
km 264 to km 340
Rajasthan[42]/Gujarat[34]
Annuity

14 76 498  Completed Larsen & Toubro Ltd., ECC Division
Indian

87
Abu Road Deesa Section near Palanpur (EW/1)
km 340 - km 350
Gujarat
NHAI

14 10 18.39  Completed Dinesh Chandra R. Agarwal
Indian

88
Palanpur - Dessa (EW-11/GJ)
Km.350.00 to Km. 372.70
Gujarat
NHAI

14 22.7 53.73  Completed Dinesh Chandra R. Agarwal
Indian

89
Deesa to Radhanpur (Package-VI)
Km 372.60 to Km 458.0
Gujarat
ADB

14 85.4 479.74  Completed Daelim Industrial Corp. Ltd.-Nagarjuna Construction Co. Ltd. (JV)
Korean - Indian JV

90
Radhanpur to Gagodhar (Package-V)
Km 138.80 to Km 245.00
Gujarat
ADB

15 106.2 410.24  Completed Jilin - Sadhbhav (JV)
China - Indian JV

91
Gagodhar to Garamore (Package-IV)
km.245.0 to km.281.3 and km 308.00 to km 254.00
Gujarat
ADB

15, 8A 90.3 479.54  Completed Daelim Industrial Corp. Ltd.-Nagarjuna Construction Co. Ltd. (JV)
Korean - Indian JV

92
Garamore to Bamanbore (Package-III)
km 254.00 tokm 182.60
Gujarat
ADB

8A 71.4 380.7  Completed Daelim Industrial Corp. Ltd.-Nagarjuna Construction Co. Ltd. (JV)
Korean - Indian JV

93
Bamnaborr - Rajkot
km 216 - km 185
Gujarat
MORTH

8B 31   Completed

94
Rajkot Bypass & Gondal Jetpur (Package-VII)
km 117.00 to km 143.00 & km 175.00 to km 185.00
Gujarat
BOT

8B 36 388.09  Completed West Gujrat Expressway Ltd.
Indian

95
Rajkot - Ribda
km 175 - km 160
Gujarat
MORTH

8B 15   Completed

96
Ribda to Gondal section (EW-10/GJ)
km 160 - km 143
Gujarat
NHAI

8B 17 40.44  Completed Tarmat - Backbone Projects (JV)
Indian

97
Jetpur to Bhiladi (Package-II)
km.117 to km 52.50
Gujarat
ADB

8B 64.5 508.5  Completed Longjian Road & Bridge Ltd
China

98
Bhiladi to Porbandar (Package-I)
km 52.50 to km.2.00
Gujarat
ADB

8B 50.5 276.07  Completed LIMAK - SOMA (JV)
Turkish - Indian JV