Chainage Chart of NHDP Phase III-A Status : 30th June 2010 |
| S. No | Contract/Stretch | NH | Length(Km) | Funded By | Status |
| Andhra Pradesh | |||||
| 1 | Hyderabad-Yadgiri (Approved Length 30) | 202 | 35.65 | BOT | Under Implementation |
| 2 | Vijayawada-Machhlipatnam | 9 | 65 | BOT | Balance for award |
| 3 | Hyderabad-Vijayawada km 40 to 221.50 |
9 | 181.63 | BOT | Under Implementation |
| Bihar | |||||
| 4 | Patna - Bakhtiarpur | 30 | 53 | BOT | Balance for award |
| 5 | Patna- Muzzaffarpur | 19 & 77 | 63 | Annuity | Under Implementation |
| 6 | Patna-Gaya-Dobhi | 83 | 125 | BOT | Balance for award |
| Chattisgarh | |||||
| 7 | End of Durg Bypass - Chattisgarh / Maharashtra Border | 6 | 82.685 | BOT | Under Implementation |
| 8 | Aurang - Raipur Km 232 to Km. 281 |
6 | 43.485 | BOT | Under Implementation |
| Delhi | |||||
| 9 | Delhi - Hissar (Delhi Portion) | 10 | 20 | BOT | Balance for award |
| Gujarat | |||||
| 10 | Kandla - Mundra Port(Approved Length 73 Km) | 8A | 71.4 | BOT | Under Implementation |
| Haryana | |||||
| 11 | Delhi/Haryana Border to Rohtak | 10 | 63.49 | BOT | Under Implementation |
| 12 | Panchkula-Barwala-Saha- Uamuna Nagar upt o UP Border | 73 | 108 | BOT | Balance for award |
| 13 | Panipat - Rohtak(Approved Length 73 Km) | 71A | 80.858 | BOT | Under Implementation |
| 14 | Rohtak - Bawal(Approved Length 97 Km) | 71 | 82.553 | BOT | Under Implementation |
| 15 | Rohtak - Hissar | 10 | 80 | BOT | Balance for award |
| Haryana[20]/Himanchal Pradesh[6.69]/Punjab[2] | |||||
| 16 | Zirakpur - Parwanoo | 22 | 28.69 | BOT | Under Implementation |
| Haryana[6]/Punjab[30] | |||||
| 17 | Ambala - Zirakpur Km. 5/735 to Km. 39/961 of NH-22 and Km. 0/0 to Km. 0/871 of NH-21 |
21, 22 | 36 | BOT | 4 LANED |
| Himanchal Pradesh | |||||
| 18 | Parwanoo - Shimla | 22 | 103 | BOT | Balance for award |
| Jharkhand | |||||
| 19 | Hazaribagh-Ranchi | 33 | 75 | Annuity | Under Implementation |
| Karnataka | |||||
| 20 | Banglore - Neelamangala | 4 | 19.5 | BOT | Under Implementation |
| 21 | Bijapur - Hungund Section (Approved Length 194 Km) | 13 | 97.22 | BOT | Under Implementation |
| 22 | Devihalli-Hassan(Approved Length 73 Km) | 48 | 77.23 | BOT | Under Implementation |
| 23 | Elevated Highway from Silk board junction to electronic city junction | 7 | 9.98 | BOT | 4 LANED |
| 24 | Hungund-Hospet (Approved Length 194 Km) | 13 | 97.89 | BOT | Under Implementation |
| 25 | Kundapur-Surathkal & Mangalore-KNT/Kerala Border | 17 | 90 | BOT | Under Implementation |
| 26 | Mulbagal - Karnataka / AP border | 4 | 11 | BOT | Balance for award |
| 27 | Neelamangala Junction on NH 4 with NH 48 to Devihalli | 48 | 81 | BOT | Under Implementation |
| 28 | Six Laning of Bangalore-Hosur Section of NH-7 km 18.750 to 33.130 |
7 | 14.38 | NHAI | 4 LANED |
| 29 | Banglore-Hoskote-Mudbagal Section km 237.700 to km 318.000 |
4 | 79.724 | BOT | Under Implementation |
| 30 | Belgaum-KNT/Goa Border | 4A | 84 | BOT | Balance for award |
| Kerala | |||||
| 31 | Charthalai - Pallakad -Thiruvananthapuram | 47 | 96.4 | BOT | Balance for award |
| 32 | Charthalai-ochira | 47 | 83.6 | BOT | Under Implementation |
| 33 | Trivendrum -Kerala/TN Border | 47 | 29 | BOT | Balance for award |
| Madhya Pradesh | |||||
| 34 | Bareli - Rajmarg Crossing | 12 | 0 | BOT | Balance for award |
| 35 | Bhopal - Bareli | 12 | 297 | BOT | Balance for award |
| 36 | Rajmarg Crossing - Jabalpur | 12 | 0 | BOT | Balance for award |
| 37 | Khalghat - MP/Maharashtra Border Km 12.600 to Km 84.70 |
3 | 82.8 | BOT | Under Implementation |
| 38 | Indore-Khalghat Km 84.00 to Km 167.50 |
3 | 80 | BOT | 4 LANED |
| 39 | Guna Bypass Km. 319/700 to Km. 332/100 |
3 | 14 | BOT | 4 LANED |
| Maharashtra | |||||
| 40 | Chattisgarh / Maharashtra Border - Wainganga Bridge | 6 | 80.055 | BOT | Under Implementation |
| 41 | MP/Maharashtra Border-Dhule | 3 | 98 | BOT | Under Implementation |
| 42 | Nagpur-Wainganga Bridge | 6 | 60 | BOT | Balance for award |
| 43 | Pimpalgaon - Nasik - Gonde | 3 | 60 | BOT | Under Implementation |
| 44 | Solapur - Maharashtra/ Karnatka Border | 13 | 30 | BOT | Balance for award |
| 45 | Pune - Khed Km 12/190 to Km.42/000 |
50 | 30 | BOT | 4 LANED |
| 46 | Kondhali - Telegaon Km 50 to Km 100 |
6 | 50 | BOT | 4 LANED |
| 47 | Nagpur - kondhali Km 9.2 to Km 50 |
6 | 40 | BOT | Under Implementation |
| 48 | Dhule - Pimpalgaon Km. 380/0 to Km. 265/0 |
3 | 118 | BOT | 4 LANED |
| 49 | Gonde-Vadape (Thane) Km. 440/000 to Km. 539/500 |
3 | 100 | BOT | Under Implementation |
| Orissa | |||||
| 50 | Chandikhole-Duburi | 200 | 39 | BOT | Balance for award |
| 51 | Duburi - Talchar | 200 | 98 | BOT | Balance for award |
| 52 | Panikholi-Keonjhar- Rimoli | 215 | 106 | BOT | Balance for award |
| 53 | Rimoli - Roxy - Rajamunda(Approved Length 163Km) 163 to 269 Km |
215 | 96 | BOT | Under Implementation |
| 54 | Bhubneshwar-Puri(Approved Length 59 Km) Km 0.00 to Km 59 |
203 | 67 | BOT | Under Implementation |
| Punjab | |||||
| 55 | Amritsar - Pathankot (Approved Length 101Km) | 15 | 106 | BOT | Under Implementation |
| 56 | Amritsar - Wagha border | 1 | 36.22 | Annuity | Under Implementation |
| 57 | Chandigarh - Kurali | 21 | 30 | BOT | Balance for award |
| 58 | Kurali - Kiratpur | 21 | 42.9 | BOT | Under Implementation |
| 59 | Jalandhar - Amritsar Km. 407/100 to Km. 456/100 |
1 | 49 | BOT | Under Implementation |
| Rajasthan | |||||
| 60 | Deoli - Kota | 12 | 83 | BOT | Under Implementation |
| 61 | Jaipur-Reengus(Approved Length 52.65 Km ) | 11 | 54 | BOT | Under Implementation |
| 62 | Jaipur-Tonk - Deoli(Approved Length 148.77 Km ) | 12 | 150 | BOT | Under Implementation |
| 63 | Kota - Jhalawar | 12 | 95 | BOT | Balance for award |
| 64 | Reengus - Sikar | 11 | 41 | BOT | Balance for award |
| 65 | UP/Rajasthan Border- Bharatpur | 11 | 21 | BOT | Balance for award |
| 66 | Mahua-Jaipur Km. 120 to Km 228 |
11 | 108 | BOT | 4 LANED |
| 67 | Bharatpur-Mahua km. 63 to Km. 120 |
11 | 57 | BOT | 4 LANED |
| Tamil Nadu | |||||
| 68 | Karaikudi - Ramanathapuram | 210 | 100 | BOT | Balance for award |
| 69 | Kerala/TN Border - Kanyakumari | 47 | 56 | BOT | Balance for award |
| 70 | Krishnagiri-Tindivanam | 66 | 170 | BOT | Balance for award |
| 71 | Nagapatanam-Thanjarur | 67 | 74 | BOT | Balance for award |
| 72 | Pondicherry - Tindivanam | 66 | 38.61 | BOT | Under Implementation |
| 73 | Trichy - Dindigul | 45 | 88.273 | BOT | Under Implementation |
| 74 | Trichy - Karur | 67 | 79.7 | BOT | Under Implementation |
| 75 | Two Laning of Trichy - Karaikudi and Trichy Bypass(Approved Length 100 Km) KM 10.00 to Km 94.00 & Km 110.016 to Km 135.930 |
210 & 67 | 110.372 | Annuity | Under Implementation |
| 76 | Madurai-Arupukottai-Tuticorin km 138.8 to km 264.5 |
45B | 128.16 | BOT | Under Implementation |
| 77 | Thanjarur - Trichy km 80 - km 135.750 |
67 | 56 | BOT | Under Implementation |
| 78 | Salem-Ulundrupet (BOT-1/TN-06) km. 0.313 to km. 136.670 |
68 | 136.357 | BOT | Under Implementation |
| Tamil Nadu[61.47]/Andhra Pradesh[63.23] | |||||
| 79 | Tirupati -Tiruthani - Chennai(Approved Length 125.5 Km) Km 274.800 - Km 341.6 to Km 0.00 to Km 59.6 |
205 | 124.7 | BOT | Under Implementation |
| Uttar Pradesh | |||||
| 80 | Delhi/UP Border to Meerut | 58 | 46 | BOT | Balance for award |
| 81 | Sitapur - Lucknow Km 488.27 to km 413.20 |
24 | 75 | BOT | Under Implementation |
| 82 | Meerut-Muzaffarnagar Km 52.250 to Km.131.00 |
58 | 79 | BOT | Under Implementation |
| Uttar Pradesh[21]/Uttaranchal[59] | |||||
| 83 | Muzaffarnagar - Haridwar (Approved Length 77 ) | 58, 72 | 80 | BOT | Under Implementation |
| Uttar Pradesh[24.75]/Rajasthan[20.25] | |||||
| 84 | Agra - Bharatpur km 17.756 - km 63 |
11 | 45 | BOT | 4 LANED |
| Uttaranchal | |||||
| 85 | Haridwar - Dehradun (Approved Length 69) | 72 | 39 | Annuity | Under Implementation |
| West Bengal | |||||
| 86 | Barasat - Bangaon | 35 | 60 | BOT | Balance for award |
| Total Length | 6274.512 | ||||
|
|