Information regarding status of Issue of NOC for setting up of petrol/ gas outlets aong National Highways with NHAI in Corridor Management Division w.e.f. 01.04.2007  (as on 31.1.2008)
Sl.No. Name of Oil Company
Date of Receipt of application from Project Director at NHAI, HQ  NH No. PIU/CMU Location (KM) Present Status
Remarks
1 HPCL 27.4.2007 1 Ambala  Km. 270.073 (LHS)  Approved
(approval conveyed to PD on 17.10.2007)
Approved
2  IBPCL 8.5.2007 1 Ambala  km 188.090 (LHS)  letter sent to PD on 17.1.2007 (for compliance of Ministry` s letter dt. 15.1.2008)  
3 BPCL 27.8.2007 1 Ambala km 250.141 (RHS)  Proposal sent to Ministry on 06.11.2007  
4 IOCL 20.9.2007 1 Ambala km 209.518 (RHS) under procees   
5 HPCL 19.4.2007 2 Durgapur  Km. 463.112 (RHS) sent to Ministry on 10.4.2008  
6 HPCL 31.7.2007 2 Durgapur  Km. 440.579 (LHS) under procees   
7 BPCL 25.09.2007 2 Durgapur Km 511.068 (RHS) letter sent to PD on 2.11.2007 for compliance  
8 BPCL 4.10.2007 2 Durgapur km 479.405 (LHS) Letter sent to PD on 14.03.2008  
9 BPCL 24.10.2007 2 Mathura 159.930 (RHS) Proposal returned to PD on 31.12.2007  
10 IOCL 2.11.2007 2 Mathura Km 55.224 (RHS) Proposal returned to PD on 5.12.2007  
11 IOCL 18.2.2008 2 Durgapur km 462.546 (LHS) sent to Ministry on 7.04.2008  
12  Vanaz Engineers Ltd. 30.4.2007 4 Pune  km 727.365 to km 737.392 (LHS) Letter sent to PD  on 05.09.2007 for compliance  
13 IOCL 24.07.2007 4 Vellore  km 96.800 to km 96.867 (LHS) Proposal returned to PD on 24.09.2007  
14 RIL  4.4.2007 5 Bhubaneshwar Km. 10.310 (RHS)
Proposal retunred to PD for compliance on 14.08.2007  
15 Pan Fuel Tech (P) Ltd. 20.4.2007 5 Visakhapatnam  km 711.210 to km 711.235 (LHS) Approved and conveyed to PD on 12.11.2007 Approved
16 Shell India Marketing Pvt. Ltd. 9.4.2007 5 Visakhapatnam  Km. 18.535 to km 18.580 (LHS)  letter sent to PD on 28.9.2007 for compliance  
17 IOCL 20.4.2007 5 Visakhapatnam  km 712.00 (LHS) Proposal returned to PD on 5.12.2007  
18 Shell India Marketing Pvt. Ltd. 20.4.2007 5 Visakhapatnam  km 693.444 (RHS) Approved and (conveyed to PD on 19.10.2007) Approved
19 Shell India Marketing Pvt. Ltd. 23.4.2007 5 Vijayawada  km 395.500  Proposal returned to PD on 21.9.2007 for compliance  
20 BPCL 5.06.2007 5 Visakhapatnam  km 1285.324 to km 470.8 (RHS) Approved
(approval conveyed to PD on 9.10.2007)
Approved 
21 HPCL 3.01.2008 5 Srikakulam km 493.299 to km 493.355
(LHS)
Proposal returned to PD on 21.1.2008  
22 IOCL 17.7.2007 7 Krishnagiri   km 34.678 to km 34.723 (LHS) ) under procees   
23 IOCL 14.5.2007 7 Krishnagiri  km 93.057 to km 93.092    (RHS)  Proposal returned to PD on 5.09.2007 for compliance  
24 IOCL 16.4.2007 8 Manor  Km 309.400 (LHS) Sent to Ministry on 04.12.2007   
25 IOCL 16.4.2007 8 Manor Km 294.235 (LHS) Sent to PD on 18.02.2008 for compliance  
26 IOCL 30.5.2007 8 Chiloda  Km 396.136 (RHS)  Sent to PD on 01.11.2007 for compliance  
27 IOCL 3.07.2007 8A Palanpur km 340.800 (RHS) Proposal returned to PD on 13.11.2007   
28 HPCL 13.4.2007 46 Vellore  km 123.192 to 123.237  ( RHS ) Proposal returned to PD on 7.9.2007 for compliance  
29 IOCL 18.5.2007 46 Krishnagiri  km 49.731 to km 49.785 (LHS) Proposal returned to PD on 7.9.2007 for compliance  
30 BPCL 24.5.2007 46 Vellore  km 111.643 to km 111.682     ( LHS ) Sent to Ministry on 27.2.2008  
31 HPCL 10.8.2007 46 Vellore km 127.862 to km 127.917 (LHS) Sent to PD on 26.11.2007  
32 IOCL 3.10.2007 46 Vellore Km 102.319 to km 102.364 (RHS) Proposal returned to PD on 6.12.2007  
33 IOCL 11.12.2007 46 Vellore km 137.413 to km 137.459  Proposal returned to PD on 21.1.2008  
34 BPCL 16.5.2007 79 Bhilwara  Km  65 to 66 (RHS)  Sent to PD on 8.08.2007 for compliance  
35 BPCL 1.6.2007 79A Bhilwara  Km 26 to Km 27 (RHS) Sent to PD on 7.08.2007 for compliance  
36 HPCL 10.08.2007 14 Palanpur km 358.580 proposal returned to PD on 9.1.2008  
37 IOCL 12.12.2007 8A Palanpur km 349.950 (RHS) Proposal returned to PD on 15.1.2008
38 BPCL 5.10.2007 24 Ghaziabad Km 29.300 Proposal returned to PD on 28.11.2007